Resolved
Agreed that consideration of this item be deferred pending its consideration by the Overview and Scrutiny Panel at their meeting on 9 th November 2004.
Cabinet agreed this item on Thursday 4 November 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that consideration of this item be deferred pending its consideration by the Overview and Scrutiny Panel at their meeting on 9 th November 2004.
2.1The Council decided in December 2003 that a “ member-led review of the District Council’s base budget, to include fees and charges but not to exclude any potential restructuring of existing arrangements for the delivery of services be undertaken with a target of identifying an overall saving of at least 2% in net expenditure”.
2.2In September 2004 the Council decided to endorse a financial strategy “based around that that described in (the table below) with a minimum increase in Band D Council Tax for 2005/06 amounting to £12 per annum”.
2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2010/ 2011/ 2005 2006 2007 2008 2009 2010 2011 2012 £M £M £M £M £M £M £M £M Budget 16.7 18.2 20.3 21.8 23.6 25.3 26.6 27.9 REDUCTIONS -0.5 -1.5 -2.0 -2.5 -3.5 -4.0 -4.5 Reduced Budget 16.7 17.7 18.8 19.8 21.1 21.8 22.6 23.4 Total Funding 14.0 15.2 16.6 17.8 19.0 20.4 21.4 22.5 Use of reserves 2.7 2.5 2.2 2.0 2.1 1.4 1.2 0.9
£ £ £ £ £ £ £ £ Council Tax 94.54 106.54 118.54 130.54 142.54 154.54 166.54 178.54 Increase % 14.5% 12.7% 11.3% 10.1% 9.2% 8.4% 7.8% 7.2% Note: Savings will need to increase further to approximately £5.5M post 2011/12 3. BASE BUDGET REVIEW
3.1Executive Councillors have discussed the base budget review with officers and this has led to the identification of areas where net reductions can be achieved without reducing levels of service.
3.2The following table shows the total impact and Annex A shows the individual items:
2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2005 2006 2007 2008 2009 2010 £000 £000 £000 £000 £000 £000 Net Reductions -557 -532 -588 -578 -578 -578
3.3The Forecast budget for 2005/06, before any reductions, is £18.2M and so £532k represents a 3% reduction. It also slightly exceeds the level of saving assumed in the strategy approved by the Council.
4. REVIEWING THE MEDIUM TERM PLAN
4.1The financial forecast presented to Council in September updated the approved MTP for various technical items (pension contributions, interest rates and inflation) but did not take account of any necessary variations to existing schemes or any need for additional bids.
4.2Officers have been reviewing the spending profile for all schemes in the light of any unavoidable delays or new information. The Capital Contingency has been renamed as Social Housing Grant to reflect the intention for its creation. Reductions have been proposed in some cases where schemes can be carried out for less or the scheme is no longer considered to be the value for money that was originally assumed. There are also some increases due to additional costs or from new unavoidable pressures – often as a result of Government decisions.
4.3Annex B shows the current position with all of the proposed variations to the approved plan being shaded. The plan is broken down into sections that reflect the degree of opportunity to make further variations. For example there is no opportunity to make changes to schemes that are already fully committed. Some of the categories are still to be updated for the latest information available – some of the partially committed schemes may by now be fully committed or additional schemes may have had their funding released by Cabinet.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MEDIUM TERM PLAN 2005: 2010: PROGRESSReport | 49 KB | DownloadRead as text |
PDF |
MTP schemes appendixAppendix | 144 KB | Download |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.