Ramsey Leisure Centre Management Committee: expired April 2009 approved this item on Monday 25 July 2005. Below is the council's own wording, with the papers it was decided on.
RESOLVED that work to repair and renew car park fencing at Ramsey Leisure Centre be approved at an estimated cost of £1,200. (f) Pool Problems The Centre Manager reported that a problem had arisen resulting in closure of the pool on the afternoon of 18th July 2005. High levels of chlorine had been dispersed into the pool and the water flow was found to be incorrect. Initial consultation with technicians had revealed the need to replace a motor ... view the full minutes text for item 12.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Ramsey Leisure Centre Management Committee: expired April 2009
RAMSEY LEISURE CENTRE 25TH JULY 2005 MANAGEMENT COMMITTEE
MANAGER’S REPORT (Report by the Centre Manager)
1. PERFORMANCE INDICATORS
Please refer to Annex A.
2. ADMISSIONS
Please refer to Annex A.
Admissions are for the period April 2005 - June 2005 inclusive. The admissions have decreased slightly against last year’s actual and this year’s target. The building work for the extension of the gym and subsequent reduction in the level of service provided, combined with the closure of the sports hall for five weeks from April 11th for work identified through the Condition Survey, have both had a significant impact on the admissions. However, some level of service has been provided throughout the extension project (barring 4 days in December) and activities were offered in alternative venues during the sports hall closure.
Total Public Admissions for the first quarter are 31,447 compared to last year’s figure of 33,697 and the target of 37,734, falls of 7.0% and 20% respectively. However a drop of only 2,000 admissions during the various closures experienced from early April to mid-May would suggest that with all facilities open, last year’s admissions and thus income, would have been exceeded and this year’s targets achievable.
2.1Swimming - Public
Total swimming admissions have reached 8,947 compared to last year’s 9,419 and the target of 9,500.
There has been a fall in recreational swimming right across the board resulting in an overall drop of 5% (487 admissions). This will undoubtedly reflect the closure of the sports hall and limited gym provision. An improvement in recreational swimming is sought and a summer swimming promotion should assist in this objective. Aquafit on the other hand has bucked the trend and increased by 8% on last year’s same quarter.
Income for public swimming reflects the fall in admissions and shows a deficit of 5%, a figure of £686. 2.2 Swimming - Lessons
The admissions for the first quarter compare favourably with last years first quarter. The 05 - 06 quarter has exceeded 04 - 05 by 12%, almost 600 admissions but this does reflect the early Easter in 2005 and consequently an extra week of swimming lessons.
The income ‘actual’ figure of £23,942 compares to the target of £22,258 extremely well, an increase of 8%.
2.3Fitness Suite and Advantage
Combining the two income figures of Fitness Suite and Advantage ‘as one’, the actual income is currently £41,796 compared to the target figure of £48,348, a deficit of 16%. However taking into consideration the limited gym provision from 1st April to 7th May, the effects were perhaps more far reaching than anticipated. The Impressions Brand Manager, who will be presenting future reports concerning Impressions and Advantage to the Management Committee, and the Centres Fitness Manager, are working very hard to improve the situation and early signs are good with the uptake for the 2005 Commit to get Fit Campaign being the highest in the District.
2.4Vending
Income is down by almost 5%, £327, which again taking into consideration the reduced facilities offered in the first 6 weeks of the financial years operation is a good performance.
The vending profit and vending profit margin compared to a target of 40% both stand at 72, but these have both been affected by incorrect coding of original orders by staff at both Ramsey and Sawtry Leisure Centre’s. Accountancy is now aware of the situation but at the time of writing this report the PI’s have not yet been updated.
2.5Other (Indoor Activities)
2.5.1 Due to a five-week closure indoor activities were expected to be well behind targets and that situation has transpired. The first quarter income is disappointing at £14,807 compared to the target of £18,626, a deficit of 20%. Admissions have also fallen behind targets, reaching just 7,655 against the target of 11,875.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Ramsey Leisure Centre Management Committee: expired April 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Termination of Joint CommitteesRESOLVED (a) that any balance remaining on the repairs and renewals fund on the closure of the separate accounts for ...
Leisure Centre Management AgreementRESOLVED (a) that subject to approval by the District Council of the recommendations in a report attached to that now...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.