Resolved
RESOLVED that the financial position in the current year and the budget forecast for 2009/2010 be noted.
Ramsey Leisure Centre Management Committee: expired April 2009 noted this item on Monday 2 February 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the financial position in the current year and the budget forecast for 2009/2010 be noted.
AGENDA ITEM NO: RAMSEY LEISURE CENTRE MANAGEMENT COMMITTEE 2 FEBRUARY 2009
2008/09 REVENUE MONITORING & 2009/10 REVENUE BUDGET (Joint Report by the Treasurer, Leisure Centre Co-ordinator and Centre Manager)
1 PURPOSE
1.1This report provides the Committee with details of the estimated outturn for the current year and the budget for 2009/10.
2. THE CURRENT YEAR (2008/09)
2.1The 2008/09 estimated outturn shown in Annex A indicates an overall reduction of £31k in Net Expenditure when compared to the original budget. The reasons for this variation are shown on the summary page of Annex A and are commented on below.
2.2Policy Changes – the items shown under this heading arise as a result of Cabinet decisions or, in the case of virements, following the completion of approval procedures laid down in the Code of Financial Management. Most of the variation at Ramsey in this section is due to the change in the savings target for this year, these have been achieved from savings on fuel bills.
2.3Technical items – technical items generally arise as a result of a revision of assumptions used in the original budget, usually as a result of actual information becoming available. They can also arise when the accounting regulations governing Local Authority accounts are amended. i) Inflation – where actual inflation on certain types of expenditure varies from the rate assumed in the original budget extra costs arise. The only variations this year relate to the pay award, 3% was allowed for in the original budget but the actual award was 3.3% and National Non Domestic Rates charges. ii) Capital Charges – actual capital expenditure in the current and the previous year affect the capital charges that have to be made. Delays to the redevelopment scheme have resulted in charges this year being lower than expected. Capital charges are also affected by the revaluation of the assets which takes place every 5 years, this can lead to large variations. The revaluation took place this year but only produced a small variation at Ramsey (£6k). iii) Central Support Recharges – the time spent on carrying out work for the Leisure Centres varies from year to year, the recharges have been altered to reflect the latest trends. Where the recharges are not time based, the basis of the allocation is regularly reviewed to ensure recharges are fair and this process can also lead to variations in the recharges. iv) Irrecoverable VAT – the Inland Revenue have announced that Local Authorities will be exempt from these regulations in 2008/09. Initially it was thought that this would continue into future years but recent announcements have confirmed that we will have to comply with the regulations in 2009/10. iv) Pension Liability (FRS17) - in order to comply with Financial Reporting Standard 17 estimates based on actuaries reports have been made and included in the latest figures.
2.4Unplanned Budget Variations – these arise where unexpected volume changes or events occur which have a financial impact that cannot be accommodated within the existing budget. The Centre Manager and the Impressions Brand Manager now have responsibility for their own budgets at each Centre and the variations below are split accordingly:-
i) Impressions/Advantage –Impressions is expected to outturn £9k under the budget target level. The income from memberships has taken a downturn because of the economic climate, however, expenditure has been kept to a minimum to offset the reduction in income. ii) Centre Managers Income/Expenditure – Overall, the budgets under the direct control of the Centre Manager are expected to be £8k under the budget target. Income is likely to be only slightly (£3k) below the budget target. Expenditure on general running costs is being kept to a minimum and as a result is likely to be £11k lower than the budget target. This saving is mainly on staffing costs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RLC Committee Annex AAppendix | 38 KB | Download |
PDF |
RLC Committee Annex BAppendix | 38 KB | Download |
PDF |
Revenue Monitoring (2008/09) & Revenue Budget (2009/10)Report | 85 KB | DownloadRead as text |
Follow Ramsey Leisure Centre Management Committee: expired April 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Mar 2009 | Termination of Joint CommitteesRESOLVED (a) that any balance remaining on the repairs and renewals fund on the closure of the separate accounts for ... | Decided | Open |
| 2 Feb 2009 | Election of ChairmanRESOLVED that Councillor E R Butler be elected as Chairman of the Management Committee. | Decided | Open |
| 2 Feb 2009 | Leisure Centre Management AgreementRESOLVED (a) that subject to approval by the District Council of the recommendations in a report attached to that now... | Approved | Open |
| 3 Nov 2008 | Final Accounts Update 2007/08RESOLVED (a) that minor changes to the Financial Statement for Ramsey Leisure Centre Management Committee 2007/08 acc... | Noted | Open |
| 21 Jul 2008 | Final accounts 2007/08 and budget monitoring 2008/09RESOLVED that the outturn position for the 2007/08 financial year and current expected variations for 2008/09 be rece... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.