MEDIUM TERM PLAN: REQUEST FOR RELEASE OF FUNDS

Approved Executive 1 paper

Cabinet approved this item on Thursday 13 October 2005. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

Approved the release of the relevant funding for a programme of maintenance work at the District’s leisure centres and a contribution towards a partnership project for an indoor activity hall at the Grafham Water Centre as included in the Council’s Medium Term Plan.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Background

2.1Council, at its meeting in December 2003, decided that specific prior approval be sought and obtained from the Cabinet before MTP schemes/projects are implemented.

2.2Officers have identified which schemes that they wish Cabinet to consider releasing funding for at this meeting and have discussed them with the relevant Executive Councillor.

2.3Annex A summarises and the succeeding Annexes detail, the schemes where release of funds is now requested.

Recommendation

3.1The Cabinet is recommended to release the funding shown in Annex A.

ACCESS TO INFORMATION ACT 1985 Budget and MTP reports Previous requests for releases

Contact Officer: Steve Couper Head of Financial Services 01480 388103 ANNEX A

SUMMARY Net Revenue Impact - £’000 Net Capital - £’000 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ Annex 2005 2006 2007 2008 2009 2010 2005 2006 2007 2008 2009 2010 B Leisure Centres Future Maintenance 9 17 17 17 17 353 C Grafham Water Centre Partnership Contribution 1 1 1 1 20

Total amount for which release now requested 9 18 18 18 18 373 ANNEX B

134B & 608 Leisure Centre Future Maintenance Simon Bell

Financial Impact Net Revenue Impact Net Capital 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2004 2005 2006 2007 2008 2009 2010 2004 2005 2006 2007 2008 2009 2010 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 Approved Budget 11 27 39 51 67 423 245 233 256 350 Already released 2 4 4 4 4 70 0 0 0 0 Amount for which release 9 17 17 17 17 353 0 0 0 0 now requested

Justification for Release

2005-06 is Year 3 of the 5 year Condition Survey work at the Leisure Centres. Progress in years 1 & 2 has been particularly successful and now that all work for year 2 has been completed this year’s programme can commence. Whilst Ramsey and Sawtry have only relatively minor elements to complete, St Neots has a variety of outstanding issues, Huntingdon requires improvements to its pool building and St Ivo needs to continue its refurbishment initiatives commenced in 2003. Management of the programme will be between the Centre Management, Environment and Transport and external specialists. Budget includes fees. ANNEX B

58 Grafham Water Centre Partnership Contribution Jo Peadon

Financial Impact Net Revenue Impact Net Capital 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2009/ 2004 2005 2006 2007 2008 2009 2010 2004 2005 2006 2007 2008 2009 2010 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 Approved Budget 0 1 1 1 1 1 10 10 Already released 0 Amount for which release 0 0 1 1 1 1 20 now requested

Justification for Release The Grafham Water Centre project is a partnership project with Cambridgeshire County Council and the New Opportunities Fund PE & School Sport programme. The HDC funding is a contribution towards a £750k project for an indoor activity hall providing facilities for archery and climbing as well as a range of other indoor sports.

Grafham Water Centre is a unique facility in Huntingdonshire providing a wide range of outdoor pursuits to schools, businesses and the general public and has worked with the Council’s Leisure Development Team in providing subsidised access to Huntingdonshire residents as part of its summer activity programme for a number of years. This arrangement will be continued for a further period as a result of assisting with his project.

Building work is due to commence in the Autumn of 2005.

Contributors: NOF £400k CCC £330k HDC £20k Total £750k

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MEDIUM TERM PLAN: REQUEST FOR RELEASE OF FUNDSReport 26 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
IC
Councillor Ian Cyril BatesVice-Chair, present
MJ
Councillor Mrs Jean ChandlerMember, present
NG
Councillor Nick GuyattMember, apologies
AH
Councillor Andrew HansardMember, present
DP
Councillor Derek Peter Holley, OBEChair, present
MP
Councillor Mrs Paula Jayne LongfordMember, present
MD
Councillor Mrs Deborah Christine ReynoldsMember, present
TV
Councillor Terence Victor RogersMember, present
LM
Councillor Lawrence Michael Simpson(known as Mike)Member, present

On this subject at Huntingdonshire

Search all
  1. MEDIUM TERM PLAN: REQUEST FOR RELEASE OF FUNDSThis decision
  2. 2025/26 Revenue Budget & Medium Term Financial Strategy (2026/27 to 2029/30); including the Capital ProgrammeApproved
  3. Final 2025/26 budget and medium-term financial strategy (2026/27 to 2029/30) including the capital programmeApproved
  4. 2025/26 revenue budget and medium term financial strategy (2026/27 to 2029/30) including the capital programmeDecided
  5. Final 2024/25 budget and medium-term financial strategy (2025/26 to 2028/29) including capital programmeApproved
  6. Final 2023/24 revenue budget & medium-term financial strategy (2024/25 to 2027/28); including the capital programmeApproved

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies