Resolved
The release of relevant funding from the MTP for the schemes listed in Annex A to the report was approved.
Cabinet approved this item on Thursday 16 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
The release of relevant funding from the MTP for the schemes listed in Annex A to the report was approved.
2.1The Council considered the draft budget and MTP report at its December meeting and agreed that, having regard to the implications for future spending and Council Tax levels, Directors review with appropriate Executive Councillors the need for schemes/projects included in the MTP but not yet started and that specific prior approval be sought and obtained from the Cabinet before such schemes/projects are implemented.
2.2Officers have considered which schemes have wholly or partly started with reference to the following definitions:
STARTED • The staff have been appointed and/or a legally binding contract is in place for all aspects. • Some of the staff have been appointed or a legally binding contract is in place for part of the scheme and there is no sensible option to avoid or defer those elements that are not yet legally committed. • The scheme is based on a partnership and all constituent projects have been agreed with those partners and they have reserved funding for them in the current year.
PARTIAL START • Some of the staff have been appointed or a legally binding contract is in place for part of the expenditure and there is a practical cost- effective option to not carry out the full scheme at this time. • The scheme is based on a partnership and some individual projects have been agreed with those partners and they have reserved funding for them in the current year.
2.3Officers have subsequently identified which schemes that they wish Cabinet to consider releasing further funding for and have discussed them with the relevant Executive Councillor.
2.4Annex A summarises and the following Annexes detail the schemes where release of funds is now requested. 3. RECOMMENDATION
3.1The Cabinet is recommended to release the funds shown in Annex A.
ACCESS TO INFORMATION ACT 1985 None
Contact Officer: Steve Couper Head of Financial Services 01480 388103 ANNEX A
SUMMARY Net Revenue Impact (£’000) Net Capital (£’000) 2005/ 2006/ 2007/ 2008/ 2009/ 2010/ 2005/ 2006/ 2007/ 2008/ 2009/ 2010/ Annex 2006 2007 2008 2009 2010 2011 2006 2007 2008 2009 2010 2011 B 192 - Vehicle Replacement Programme – 06/07 9 18 18 18 18 362 C 22 - CCTV Improvements – Leisure Centres 1 1 1 1 1 20 D 39B & 309/442/441 - Disabled Facilities Grants 25 50 50 50 50 995 E 611 - Discretionary Repair Loans / Grants 6 12 12 12 12 233 F 662 - Community Information Centres 44 G 450 - Replacement Photocopiers 1 1 1 1 1 1 27 H 651 – Herne Rd STW Replacement 1 2 2 2 2 30 I 652 – Closed Church Yards Maintenance 25 15 15 15 15 J 469/620 – Crime and Disorder – Lighting 1 1 1 1 1 23 Improvements K 389 – Local Transport Plan 2 4 4 4 4 87 L 474 – Safe Cycle Routes 5 10 10 10 10 205 M 460 – CCTV – Camera Replacements 1 1 1 1 1 13 N 250 – St Neots Transport Bid 2 4 4 4 4 83 O 472 – Accessibility Improvements 1 1 1 1 1 31 P 361 – Huntingdon Transport Strategy 2 4 4 4 4 74 Q 362 – St Ives Transport Strategy 2 4 4 4 4 76 R 479 – Community Transport Funding 34 34 34 34 34 S 132 – Railway Station - Improvements 1 1 1 1 1 15 T 400 – Bus Shelter Provision 1 2 2 2 2 15 U 672 – Concessionary Fares 232 232 232 232 232 V 480 – Implementation of the Car Parking -91 -82 -82 -82 -82 380 Strategy W 603 – AJC Small Scale Improvements 3 6 6 6 6 112 X 674 – Heart of Oxmoor 36 1 1 1 1 1 1980 -2161 Y 336 - Huntingdon Leisure Centre - Impressions -1 -1 -1 -1 150 Expansion
Total amount for which release now requested 37 309 321 321 321 321 2007 743 ANNEX B
192 - Vehicle Replacement Programme – 2006/07 Robert Ward
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MEDIUM TERM PLAN: REQUESTS FOR RELEASE OF FUNDSReport | 109 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.