Resolved
Noted the Council’s management of assets against National Property Performance Indicators for 2005/06 and approved the performance indicator information contained in Appendix A to the report.
Cabinet noted this item on Thursday 21 December 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the Council’s management of assets against National Property Performance Indicators for 2005/06 and approved the performance indicator information contained in Appendix A to the report.
2.1Information on property performance indicators has been produced annually since they were introduced in 2002. Under new guidance last year three indicators were dropped and the number of others introduced to bring the total required up from 12 to 19. Section 3 reports on these indicators.
2.2The asset management implications of the use of resources assessment undertaken at the beginning of 2006 is considered in Section 4.
2.3Following further consultations, additional indicators are proposed for the current year and these are referred to in Section 5.
3. REPORT ON THE INDICATORS
3.1The indicators are now called Performance Management Indicators (PMI’s). Outcomes for comparable indicators for 2004/05 and 2005/06 are set out in Appendix A. The following paragraphs provide a brief commentary on the indicators and, where appropriate, comparison is made with other authorities using information from the IPF Asset Management Network (IPF).
3.2PMI 1 Condition and Required Maintenance
3.2.1 This is intended as a national indicator and the previous indicator has been expanded to include annual changes in expenditure, maintenance spend per square metre and a split between planned and responsive maintenance. The purpose is to measure the condition of assets, changes in condition and the spend on maintenance. It applies to all property where the Council has a repairing obligation.
3.2.2 In PMI 1A, the percentages within categories A-D have remained broadly the same as the previous year. Compared to the operational properties of other authorities, the 5% in A is low (IPF average 18%) while B at 86% is within the upper quartile (IPF average 58%). This position should change over the next few years as more properties move from satisfactory to good following refurbishment and the opening of new offices. 3.2.3 With regard to required maintenance (PMI 1B), the Council is well below the average for urgent work (1% compared to 12%) but has a relatively high figure for essential maintenance (55% compared to 42%)
3.2.4 The increase in required maintenance by cost (PMI 1C) relates entirely to leisure buildings where a further condition survey, as part of a 10 year programme, has recently been carried out.
3.2.5 Information is now included under PMI 1D on maintenance costs. The figure per square metre has fallen from £10.69 to £9.74 since the previous year. For the first time, the split between planned and responsive expenditure is provided; under best practice the aim is to move towards a higher percentage spend on planned repairs.
3.3PMI 2 A, B and C: Environmental Property Issues
3.3.1 These are also national indicators and have been expanded to include energy and water consumption in addition to costs. They apply to all operational property occupied by the Council and the purpose is to encourage efficient use of assets and year-on-year improvements in energy efficiency.
3.3.2 Energy costs of £11.25 are below the IPF average of £13.89. Water costs are above the IPF average. CO2 emissions at 0.10 are above the IPF average of 0.07.
3.3.3 Information has also been collected on energy and water consumption.
3.4PMI 3 A and B: Suitability Surveys
3.4.1 These are required for all 37 operational properties in order to assess whether buildings are fit for purpose. Based on systems used by other authorities, the relevant buildings have been assessed against the specific criteria – location, accessibility, environment, health & safety, fixtures & fittings and image. The outcome of this review is summarised below:
Score out of 30 Number 1-6 unsuitable 0 7-12 poor 2 13-20 satisfactory 29 21-30 good 6
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AMP.app A. 21.12.06Appendix | 13 KB | Download |
PDF |
Asset Management PlanReport | 18 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.