RESOLVED ( i ) that the outcome of the working group’s deliberations be endorsed and the members thanked for their investigation; and (ii) that arrangements be made for the Chairman and Vice-Chairman, together with the members of the working group, the Executive Councillor and relevant officers to meet with representatives of the Huntingdon Business Network, the Federation of Small Businesses and the Chamber of Trade to advise them of the Panel’s decision.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being
OVERVIEW & SCRUTINY PANEL 9th JANUARY 2007 (SERVICE SUPPORT)
REVIEW OF LOCAL PROCUREMENT (Report of the Working Group appointed by the Panel)
1. INTRODUCTION
1.1At their meeting held on 11th July 2006, the Overview and Scrutiny Panel (Service Support) considered the question of local procurement by the Council and the ways in which this could potentially promote the local economy within Huntingdonshire. The issue had been raised initially by the Chairman of the Service Delivery Scrutiny Panel following an approach to him by the Huntingdon Business Network who had suggested that the Council should do more to encourage and facilitate business opportunities for local suppliers to tender for Council supplies and services. A report on the subject by the Council’s Economic Development Manager and Procurement Manager was considered at a subsequent Panel meeting which was attended by a representative of Huntingdonshire Business Network. Having decided to investigate the matter further the Panel appointed Councillors D B Dew, P J Downes and R J West to form a working group for this purpose.
2. METHODOLOGY
2.1The working group has met on three occasions, and has received information from the Procurement Manager relating to:-
¾ Goods and services currently procured by the Council; ¾ Goods and services procured locally by the Council; and ¾ The percentage spend on goods and service by area.
This is attached as Appendix A. These statistics mask the origin of the goods purchased and do not show whether they were manufactured locally or simply sourced by a local supplier. A more detailed analysis would be difficult to achieve.
2.2Information was obtained from similar reviews carried out by other authorities, the reports on which have either been published on the Centre for Public Scrutiny’s website or were provided by the authorities in question. Of those available the Working Group considered those undertaken by Derbyshire County Council, Wolverhampton City Council and the London Borough of Waltham Forest.
2.3It was clear that the reviews undertaken by those authorities were extensive, involving
¾ Gathering of evidence from key stakeholders; ¾ Consultation with business interests, local Development Agency, the local Centre of Excellence, local authorities and various other bodies; ¾ Analyses of spend.
Lengthy reports were produced with a series of recommendations relating to effective engagement and raising awareness with suppliers, packaging of work, amendments to contract documentation, development of framework contracts etc.
2.4The Working Group’s attention was also drawn to a booklet jointly produced by the Office of Government Commerce and the Small Business Service designed to raise awareness of the value for money that small firms can offer, to explore the issues that can make it difficult for them to win public sector business and to set out ideas as to how local authorities can help.
2.5The Working Group were aware from the outset from the report submitted by the Economic Development Manager and the Procurement Manager that the Council’s procurement process is constrained by the European procurement regulations and that it is not permissible to discriminate in favour of local suppliers when purchasing supplies and services.
3. DELIBERATIONS
3.1The Working Group concluded that the level of the Council’s expenditure and its profile were not sufficiently large to justify carrying out a local study in depth which would have been unlikely to result in recommendations which differed from the conclusions reached by the other authorities which had already undertaken this work. The results would not have justified the considerable resources that would have had to have been committed by the Panel to complete a similar exercise.
3.2Moreover, the Working Group felt that the opportunities for increasing Council spend in equipment and materials is very limited, although there may be some scope for improvement in the areas already well represented such as construction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Proposals for Riverside Park, HuntingdonRESOLVED that the Panel broadly welcome the scheme but feel that Phase II should be regarded as aspirational only at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.