A14 ELLINGTON TO FEN DITTON – FURTHER PUBLIC CONSULTATION
RefusedScrutiny5 papers
Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being refused this item on Tuesday 13 February 2007. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Council be recommended - (a) to support the orange route, subject to consideration by the Highways Agency as to the best alignment and environmental solution for Brampton between the orange and brown route to the west of the A1 as outlined in the report now submitted, (b) to reject the blue route, including variation 2, on the grounds of their unacceptable and detrimental impact on both Brampton and Fenstanton ; (c) to reject the brown route on the grounds of the potential impact on the Buckden North and South landfill sites and associated issues that may arise from the adoption of that element of the route as outlined in the report now submitted; (d) to authorise the Director of Operational Services, after consultation with the ... view the full minutes text for item 77.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being
Background
2.1The proposed improvement of the A14 has been the subject of a number of previous studies and consultations, the fundamental study being the 2001 Cambridge to Huntingdon Multi-Modal Study (CHUMMS). In its final report of August 2001, CHUMMS recommended a strategy of trunk road and local highway improvements combined with the provision of additional high quality public transport.
2.2The CHUMMS proposals were considered by Full Council on 26th September 2001. The resolutions agreed at that meeting are attached at Annex A. Key issues of that resolution were that action needed to be taken as a matter of urgency to address the problems of the A14, that a comprehensive package of improvement measures should be prepared and that Government should commit sufficient funding to implement the overall comprehensive package.
2.3In 2005, the Highways Agency subsequently published a set of proposals to improve the A14 between Ellington and Fen Ditton. This took the form of public consultation on two strategies for the new road, namely the CHUMMS strategy and an Alternative Proposal.
2.4The principle proposal within the CHUMMS strategy was for the provision of a new road south of Huntingdon and Godmanchester. This would be three lanes in each direction, the existing A14 would become a local road allowing direct access to Huntingdon Station with less traffic using the Godmanchester town bridge, the removal of the A14 viaduct over the East Coast Main Line (ECML) and the connection of that route into the local road network. The proposals also included plans to widen the A1 to three lanes in each direction between the new Brampton Interchange and Brampton Hut and to consider future widening of the A1 to three lanes between Brampton Hut and Alconbury.
2.5The Alternative Proposal was for a proposed new road south of Huntingdon & Godmanchester, two lanes in each direction, between Ellington and Fen Drayton which would only take east-west traffic. North-south traffic would continue to use the current A14 through Huntingdon and Godmanchester and the existing Viaduct over the ECML at the railway station would be rebuilt. It was also concluded that there would be no requirement to widen the A1 as it would carry very little additional A14 traffic.
2.6These proposals were considered by Full Council on 29th June 2005, and a number of resolutions were agreed and a copy of these were contained in the formal response of the District Council to the Highways Agency dated 4th July 2005. This is attached at Annex B.
2.7As will be noted, this response was extensive but the principle issues included;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Proposals for Riverside Park, HuntingdonRESOLVED that the Panel broadly welcome the scheme but feel that Phase II should be regarded as aspirational only at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.