Resolved
Approved the release of funding for the cost of resurfacing the synthetic pitch at Huntingdon Leisure Centre.
Cabinet approved this item on Thursday 4 October 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Approved the release of funding for the cost of resurfacing the synthetic pitch at Huntingdon Leisure Centre.
2.1The Council agreed in December 2005 that, having regard to the implications for future spending and Council Tax levels, Directors review with appropriate Executive Councillors the need for schemes/projects included in the MTP but not yet started and that specific prior approval be sought and obtained from the Cabinet before such schemes/projects are implemented.
2.2Officers have identified the schemes that they wish Cabinet to consider releasing funding for and have discussed them with the relevant Executive Councillor.
2.3Annex A summarises and the following Annexes detail these requests.
3.1The Cabinet is recommended to release the funds shown in Annex A.
ACCESS TO INFORMATION ACT 1985 None
Contact Officer: Steve Couper Head of Financial Services ( 01480 388103 ANNEX A
SUMMARY Net Revenue Impact (£’000) Net Capital (£’000) 2006/ 2007/ 2008/ 2009/ 2010/ 2011/ 2006/ 2007/ 2008/ 2009/ 2010/ 2011/ Annex 2007 2008 2009 2010 2011 2012 2007 2008 2009 2010 2011 2012 B 708 Condition Survey (all Leisure Centres) 1 -8 -9 -8 -10 95 Huntingdon Leisure Centre – Synthetic pitch resurface and re-model
Total amount for which release now requested 1 -8 -9 -8 -10 95 ANNEX B
708 Condition Survey (all Leisure Centres) Project Manager – Simon Bell Huntingdon Leisure Centre – Synthetic pitch resurface and re-model
Financial Impact Net Revenue Impact Capital 2006/ 2007/ 2008/ 2009/ 2010/ 2011/ 2012/ 2006/ 2007/ 2008/ 2009/ 2010/ 2011/ 2012/ 2007 2008 2009 2010 2011 2012 2013 2007 2008 2009 2010 2011 2012 2013 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 Approved Net Budget 222 171 250 256 260 231 1,479 1,313 857 498 477 (Total Condition Survey) Income 3 -6 -7 -7 -8 -8 (Increased Usage) Expenditure -2 -2 -2 -2 -2 -2 (Savings on Maintenance) Amount for which release now requested 1 -8 -9 -8 -10 -10 95 (Net Revenue Impact)
Summary of Scheme
v This scheme is part of the overall Leisure Centres Condition Survey and has been marked as a year one (2007) item due to its urgent nature.
v Huntingdon Leisure Centre’s synthetic pitch was installed when the centre opened (1992) with a ten-year life expectancy.15 years hence replacement is urgently required.
v Rather than replace like with like, the proposed scheme would split the existing 7-a-side facility into two separate five-a-side surfaces with a football specific artificial surface together with inset goals and replacement fencing. v This would allow two games to occur side by side and increase the potential participation from 14 to 20 per hour, raising total annual admissions to 23,000 (from 18,000).
v Work would be carried out during a four/five week period when outdoor bookings are at their lowest. This would minimise service disruption. There will be loss of income during this period (estimated £3k) which should be quickly recouped by the attraction of the refurbished facility and the additional bookings that can be housed.
v Current income is £30k pa. Revision to the pitch will increase this to around £36k, with no increase in maintenance. Monthly brushing (£3k pa) will not increase.
Justification for Release
v Pitch repairs to the surface and fence during 2006/07 totalled £6k and this figure will further increase year on year as the pitch ages unless replacement takes place.
v During repair times customer dissatisfaction occurs when the centre has been unable to honour customer bookings. This has resulted in regular loss of income.
v Synthetic pitch hire costs up to £36 per hour and the centre receives regular complaints regarding the state of the facility as poor value for money.
v The proposed scheme has the potential to reduce annual expenditure on surface and fence repair and to increase income by up to 20%.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Medium Term Plan: request for the release of funds: Huntingdon Leisure CentreReport | 120 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.