Agreed to release £114,000 towards the re-surfacing of the synthetic pitch at St Neots Leisure Centre and £42,000 towards repairs to the pool roof at Huntingdon Leisure Centre and £38,000 towards the replacement of the dry-side boiler plant and accessibility improvements at St. Neots Leisure Centre.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
2.1The Council agreed in December 2005 that, having regard to the implications for future spending and Council Tax levels, Directors review with appropriate Executive Councillors the need for schemes/projects included in the MTP but not yet started and that specific prior approval be sought and obtained from the Cabinet before such schemes/projects are implemented.
2.2Officers have identified the schemes that they wish Cabinet to consider releasing funding for and have discussed them with the relevant Executive Councillor.
2.3Annex A summarises and the following Annexes detail these requests.
Recommendation
3.1The Cabinet is recommended to release the funds shown in Annex A.
ACCESS TO INFORMATION ACT 1985 None
Contact Officer: Steve Couper Head of Financial Services ( 01480 388103 ANNEX A
Summary of Scheme v This scheme forms part of the Condition Survey and has been marked as urgent due to its deteriorating condition. Originally scheduled for 2009 (year 3) the project has been brought forward to early 2008. To compensate, an equivalent sum has been moved from year 1 to year 3 from elsewhere in the survey. v SNLC’s large synthetic pitch was installed in 1994 with a ten year life expectancy. 13 years on it now urgently needs replacing. v Work would be carried out during a four-five week period when outdoor bookings are at their lowest. This minimises disruption to service. There will be a loss of income during this period which will be recouped by the attractiveness and anticipated additional bookings from the new high quality facility.
Justification for Release v Pitch repairs and maintenance to the regular sweeping regime during 2006/07 totalled £2.5k and this figure will increase year on year as the pitch ages. v The synthetic pitch is home to St Neots Hockey Club which contributes £10,000+ in pitch hire and hospitality trade each year. The potential loss of this group to an alternate proposed facility at Longsands School is very real should SNLC not be able to provide a playing surface to the National Hockey Association standard v During these times further customer dissatisfaction has occurred when the Centre has been unable to honour customer bookings. This has resulted in loss of income. v Synthetic pitch hire costs £48 per hour and the Centre receives regular complaints regarding the state of the facility as poor value for money. v Reduces the risk of claims against SNLC/HDC with regard to the safety of the surface. Poor seam maintenance increases the risk of hockey balls “lifting” potentially causing serious facial injuries.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.