Corporate Governance Panel noted this item on Wednesday 26 March 2008. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

RESOLVED (a) that the assurance framework attached at Appendix A to the report now submitted be endorsed; and (b) that progress made to date in the achievement of the action plan supporting the Annual Governance Statement be noted.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Panel

Background

2.1In September 2007 the Panel adopted a revised Code of Governance which sets out and describes the way in which the Council carries out its functions and complies with the principles of openness, integrity and accountability. The principles in the Code apply to elected Members and employees alike, and they are reflected in the Council’s working procedures and processes in the interests of establishing and maintaining public confidence.

2.2To ensure that the Council is meeting the code and delivering good governance an annual cycle is in place which includes:

• an annual review of governance arrangements; • preparation of an Annual Governance Statement (AGS); • implementation of an action plan associated with the AGS; • a half yearly review of progress against the action plan; and • continued reference to systems and reporting as necessary to provide assurance and support for good governance.

2.3This cycle is designed to reflect good practice in delivering a framework of assurance for Members and employees in terms of governance arrangements and to help to ensure accountability and transparency for local people and other stakeholders such as the Council’s external auditors and Government inspectors.

Annual Review Annual Governance Statement

Periodic Reports as necessary arising Implementation of from systems of assurance Action Plan

½ Yearly Review 3. ASSURANCE FRAMEWORK

3.1Appendix A sets out - against the six principles of the Code of Governance, the supporting principles and specific requirements - the sources of assurance which support the Council’s governance arrangements.

3.2As the risk register update report elsewhere on the agenda explains, a great deal of work has been undertaken on making sure that the risk register is robust. The mapping of the Council’s strategic objectives to the risks identified is underway and is expected to be completed by August 2008.

3.3The risk software is being updated with details of the current internal and external sources of assurance and the assurance level for each risk and risk control. An example is provided at Annex B. This information will also support the Council’s governance arrangements.

4. HALF YEARLY REVIEW OF GOVERNANCE ACTION PLAN

4.1At the September meeting the Panel considered the Annual Governance Statement which identified issues to be addressed over the next year to help improve further the Councils governance arrangements. Annex C identifies these issues and progress to date.

Recommendations

5.1The Panel are recommended to:

(a) endorse the assurance framework as described in section 3 and associated appendices; and (b) note progress to date in the achievement of the action plan supporting the Annual Governance Statement.

Background papers

Code of Governance Annual Governance Statement

Contact Officer: Howard Thackray, Policy & Research Manager ( 01480 388035

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ASSURANCE FRAMEWORK and annual governance statementReport 66 KB DownloadRead as text
PDF
Appendices for Covering Report Gov Panel 26 MarchReport 85 KB Download
PDF
New_ControlsAssurance0603115308 1Report 20 KB Download
PDF
Appendix cAppendix c 58 KB Download

At this meeting

Whole meeting

Who was there

6 of 7 attended
KJ
Councillor Ken James ChurchillVice-Chair, present
PJ
Councillor Peter James Downes OBEMember, present
JA
Councillor Jonathan Alexander GrayMember, present
TV
Councillor Terence Victor RogersMember, apologies
LM
Councillor Lawrence Michael Simpson(known as Mike)Member, present
CJ
Councillor Christopher John StephensChair, present
GS
Councillor Gordon Sydney Edward ThorpeMember, present

On this subject at Huntingdonshire

Search all
  1. ASSURANCE FRAMEWORK and annual governance statementThis decision
  2. Corporate governance: assurance frameworkNoted

More from Huntingdonshire Corporate Governance Panel

All decisions
MeetingDecisionOutcome
9 Mar 2016 Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... Decided Open
9 Mar 2016 External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... Agreed Open
9 Mar 2016 Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. Noted Open
9 Mar 2016 Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. Approved Open
9 Mar 2016 Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... Approved Open