Resolved
RESOLVED that the Audit and Assurance Plan be approved.
Corporate Governance Panel approved this item on Wednesday 26 March 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Assurance Plan be approved.
Internal Audit Service Internal Audit & Assurance Plan 2008 2008 Internal Audit & Assurance Plan
The Internal Audit & Assurance Plan for the period April – July 2008 has been prepared in accordance with best practice as contained in the 2006 CIPFA Code of Practice for Internal Audit.
The Code requires that Internal Audit provide an opinion on the overall adequacy and effectiveness of the Council’s internal control environment and that the opinion should inform the Annual Statement of Assurance on Corporate Governance.
The plan has been developed to take account of this requirement and provides the opportunity for reviews of corporate governance, risk management and operational controls to be undertaken as well as the more traditional financial areas.
The Code also explains for the first time, that sufficient, evidenced work must have been completed before an opinion can be given on the activity that has been reviewed. A number of reviews included in the audit plan have been taken directly from the Council’s current risk register. The Panel need to be aware that the internal audit plan is unable to provide, apart from in those areas specifically reviewed, any assurance as to the effectiveness or otherwise of the controls listed in the register.
A summary of the audits planned for the period are listed on the following pages, together with the name of the Liaison Officer responsible for dealing with any audit report or other issue that arises from an audit review. In addition to undertaking the audits detailed in the plan, a review of fraud risks is also being planned. Internal audit are also likely to be involved in providing advice and assistance to managers, advising on new project developments and dealing with any whistleblowing allegations received.
Whilst it is envisaged that all the audits contained in the plan will be undertaken, the identification of any new risks or significant changes in residual risk scores, may require audits to be substituted so as to ensure that reviews are undertaken of areas identified as being of greatest risk to the achievement of Council objectives. Chief Officers and Heads of Service will be informed of any changes before they are introduced.
David Harwood Audit & Risk Manager 4 March 2008 Audit Days
Corporate Systems
Service Delivery : T Parker 30 The CPA UoR KLOE considers a number of issues with regard to best value. This review will consider how activities are able to show that they are efficient and effective and that opportunities to review and improve processes are identified and acted upon. – what indicators are there ?
Risk Management Arrangements: S Couper 8 Inherent Risk High Residual Risk High Risk management is an important part of the CPA KLOE and the governance of the Council. This review will consider how well risk management has become embedded into the Authority’s business process, the robustness of the risk register and officer training.
Total Allocation 38
Commerce & Technology
Bailiff Service: J Barber 5 Inherent Risk Very High Residual Risk High Bailiffs are used to recover unpaid Council Tax and NNDR. This audit will examine the systems in place for referring cases to the bailiffs and the process for referring potential difficult customers to them. This area was last reviewed in 2004 and was given limited assurance.
Total Allocation 5
Central Services
Leisure Centres: R Reeves 27 To continually review across the 5 Leisure Centres specific areas of their operation. This year’s areas will be agreed with the Head of Service prior to commencement.
Management of Ill Health & Sickness: P Duerden 12 This review will re-examine the Council’s “Bradford” sickness monitoring scheme and the effects it has had on the early identification and reduction in sickness. This area was last reviewed in 2004 and was given limited assurance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
02 April 2008_audit_plan_to_CGP 260308Report | 79 KB | DownloadRead as text |
PDF |
Internal Audit service : internal audit plan 2008Report | 54 KB | Download |
Follow Corporate Governance Panel at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2016 | Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... | Decided | Open |
| 9 Mar 2016 | External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... | Agreed | Open |
| 9 Mar 2016 | Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. | Noted | Open |
| 9 Mar 2016 | Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. | Approved | Open |
| 9 Mar 2016 | Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.