RESOLVED (a) that the Transportation Team Leader be requested to invite Members to identify any additional routes within their wards; and (b) that the draft report on the prioritisation of schemes be considered by the Panel prior to its submission to the Huntingdonshire Traffic Management Area Joint Committee.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being
Background
2.1The Working Party met on three occasions and was acquainted with the role that the District Council plays with regard to cycling provision across the District. This included funding contributions through our MTP, in partnership with the County Council Local Transport Plan (LTP) budget, negotiation of S.106 agreements, provision of cycle racks and cycle route promotion.
2.2The Working Party also sought information on the level of funding provided by the County Council in relation to cycle route provision. While it became evident that there is a well-established partnership arrangement in place to fund and deliver improved cycling and walking routes within the Market Towns as part LTP strategies in place, the picture was less clear elsewhere unless as part of S.106 negotiations, such as the local cycling initiatives already secured within Yaxley.
2.3Reference was also made to the existing Cycling Strategy adopted by the Council in 2000 which contained a number of specific objectives and also an approved list of 41 priority routes for future consideration in a number of rural and urban situations. It was evident that while the urban routes were now being considered through the Market Town Transport Strategies (MTTS), it was unlikely that the majority of the more rural based routes would ever be addressed unless additional resources were made available. 2.4 Following Officer discussions with the County Council relating to similar work undertaken within South Cambridgeshire during 2006, the County Council agreed to work with the District Council to update the cycling priorities originally agreed in 2000 and to prepare an action plan for implementation. On this basis, the County Council indicated that it would consider funding an agreed programme in partnership with the District Council.
2.5The Working Party also noted that the adoption of a revised Action Plan would also give officers of both Council’s the ability to secure S.106 funding from any development that had a direct impact on any of the agreed routes within an updated Action Plan. By way of example, it was on this basis that such S.106 funding was secured within Yaxley from the original work outlined in 2000, for works that will now commence construction within the village during 2008/09. In addition to S.106 funding, the construction works will also be part- funded utilising the District Council 2008/09 ‘Safe Cycle Routes’ budget within the current MTP.
3. CURRENT POSITION
3.1Following the Panel meeting in February 2008, officers from both Council’s have met on two occasions. At the first meeting a revised list of schemes to be prioritised was agreed. This is shown at Annex A and also includes those urban-based routes from the original work in 2000 that will no longer be included in this work but will be considered separately through the MTTS or other process.
3.2At the second meeting, officers have undertaken the prioritisation exercise of the 28 routes remaining. This has been undertaken using the countywide scoring template, an example of which is included at Annex B. As noted previously by Panel, the results of this exercise will be reported to the Huntingdonshire Traffic Management Area Joint Committee on 7th July 2008, they being the body responsible for the approval of such work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Proposals for Riverside Park, HuntingdonRESOLVED that the Panel broadly welcome the scheme but feel that Phase II should be regarded as aspirational only at ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.