Received the report and noted the expenditure variations and capital and revenue impact, approved the commencement of the Medium Term Plan schemes for St Ivo Leisure Centre – Football Improvement, Huntingdon West Development and St Neots Green Corridor referred to in paragraph 2.2 and approved the commencement of the Sustainable Homes Retro-Fit scheme, subject to the Executive Councillor for Finance and Environment being consulted on the scheme’s timing in relation to the ongoing housing market.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
CAPITAL PROGRAMME MONITORING 2008/09 BUDGET (Report by the Head of Financial Services)
1. PURPOSE
1.1This report highlights the variations from the 2008/09 Capital Programme approved in February 2008 including any member or officer decisions already taken in accordance with the Code of Financial Management.
2 MONITORING INFORMATION 2.1 The Budget approved in February 2008 and subsequent adjustments are shown below:-
2008/09 Capital Expenditure Capital Programme Gross External Net Budget Contributions Budget £000 £000 £000 Approved Budget (February 2008) 16,955 1,483 15,472 Deferrals from 2007/08 4,649 3,580 1,069 21,604 5,063 16,541
New MTP Bids (paras 2.2 to 2.5) 1,425 1,295 130 Cost Variations (Annex A) -253 -128 -125 Timing Changes to 2009/10 (Annex B) -2,694 -1,027 -1,667
Capital / Revenue Variations VOIP Data Switches 90 0 90 Recycling Bins 83 0 83 Commutation 43 0 43 Community Facilities Grant (reported last time) -46 0 -46
Current Forecast 20,252 5,203 15,049
2.2This year’s MTP process has identified the following new proposals that would impact on the current year but would not be formally approved until the end of the process in February.
2008/09 Capital Expenditure MTP Bids Gross External Net Budget Contributions Budget £000 £000 £000 St Ivo L C – Football Improvements 250 500 -250 Huntingdon West Development (HGF) 700 700 0 St Neots Green Corridor (HGF) 95 95 0 Sustainable Homes Retrofit (cost of purchase) 380 0 380 1,425 1,295 130 2.3 The St Ivo scheme is fully funded from grants and S106 contributions. It shows a credit in the current year because some income will be received in advance.
2.4The Huntingdon West and St Neots Green Corridor schemes are dependent on receiving full funding from the Housing Growth Fund.
2.5The Sustainable Homes retrofit scheme is based on purchasing existing properties and fitting various items that will illustrate the benefits from improved energy usage. After conversion they will be used to demonstrate the benefits and subsequently sold. The money for the adaptations is already in the budget but not the money for purchase (a total of £500k) which will be recouped on their subsequent sale. There is also a sum of £15k running costs needed for two years included in the MTP bid. Obviously the housing market is very uncertain currently and if Cabinet agree to this scheme proceeding in principle then the relevant executive councillor will be consulted before any commitment to purchase.
2.6Annex A gives details of the cost variations of which the significant items are:
• additional costs on the Creative Enterprise Centre Industries though these are still under negotiation • a saving on VAT due to an extension to the current year of the relaxation of the partial exemption rules that prevented the Council from recovering all of its VAT.
2.7Annex B provides details of the timing changes currently identified. The original budget also included provision for a net deferral to later years of £700k. This has not been removed as past experience has shown that further deferrals emerge in the latter part of the year.
2.8There are three new transfers from revenue to capital which increase the Council’s financial flexibility.
3. REVENUE IMPLICATIONS
3.1The impact of the variations to the original budget approved in February 2008 is to reduce the net revenue expenditure by £234k in 2008/09 with further adjustments in future years, as shown below. 2008/ 2009/ 2010/ 2011/ 2012/ Revenue Impact 2009 2010 2011 2012 2013 £000 £000 £000 £000 £000 Timing Changes 2007/08 to 2008/09 -27 New MTP Bids 4 31 40 11 -3 Cost Variations -3 -6 -6 -6 -6 Timing Changes 2008/09 to 2009/10 -42 -42 Revenue/Capital Transfers -166 8 8 8 8 TOTAL FORECAST VARIATION -234 -9 42 13 -1
N.B. Revenue impact is based on 5% loss of interest 4. CAPITAL RESERVES
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.