Resolved
Recommended to full Council that the proposed Budget, Medium Term Plan and Financial Strategy and that a Council Tax increase of 4.99% (£5.76) representing a level of £121.15 for Band D properties be approved for 2009/2010.
Cabinet approved this item on Thursday 29 January 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Recommended to full Council that the proposed Budget, Medium Term Plan and Financial Strategy and that a Council Tax increase of 4.99% (£5.76) representing a level of £121.15 for Band D properties be approved for 2009/2010.
2.1This year’s process started with consideration of a financial strategy by Overview & Scrutiny, Cabinet and Council in September. The second stage was the draft MTP and Budget report, discussed by Overview & Scrutiny and Cabinet, before being considered by Council on the 3 December. Both reports highlighted the difficulty of assessing how deeply and how long the expected recession would last.
3 PROPOSED CHANGES TO THE DRAFT PLAN
3.1A number of adjustments have been necessary since the December report. A number relate to forecast higher net spending due to economic factors. These include lower interest rates in the shorter term but higher rates in the longer term, the increase in the NI rate from April 2011 and increased vacancies on industrial properties.
3.2The first two months income, since the car park tariffs were changed in October, implies that the forecast patronage was too optimistic. Allowance has therefore been made for gradual recovery of these sums over the Plan period.
3.3HM Revenues and Customs had signalled a permanent end of the Council’s loss of some VAT each year but they now do not consider their intended approach will comply with the regulations. Allowance must be made for the loss recommencing next year pending an alternative solution being found.
3.4Additional spending on statutory Disabled Facilities Grants has been included to reflect the “catch up” anticipated now that the PCT has increased Occupational Therapist resources.
3.5Detailed work has been ongoing in order to revise the bid for IT systems replacements. An increased sum has been included that better reflects the unavoidable demand for upgrades and occasional replacement systems. 3.6 Inflation provisions have been revised to reinstate the allowance for some areas of unavoidable inflation but this is more than off-set by the impact of recent falls in the level of petrol prices.
3.7The full summary is shown below:
PROPOSED CHANGES 2009/10 2010/11 2011/12 2012/13 2013/14 £000 £000 £000 £000 £000 Capital Reintroduction of provision for loss of VAT (Partial 212 44 25 22 35 Exemption) IMD Systems Replacement Bid 98 326 100 13 93 Disabled Facilities Grants 250 St Neots Footbridge (rephasing) -537 537 Inflation on above items 23 6 3 13 23 930 131 38 141
Revenue ( - = less cost ) Fuel inflation allowance reduced from previous -136 -136 -136 -136 -136 assumptions Increase in NI rate from April 2011 98 103 109 Other inflation 45 45 45 30 -164 Provision for loss of VAT (Partial Exemption) 140 140 140 140 140 Car Parking charges and penalties 140 126 102 68 34 NNDR Relief on small industrial properties in 2009/10 -30 IMD Systems Replacement Bid 8 6 20 20 20 Temporary saving on toilet maintenance -30 Increased vacancies on Industrial properties 80 Variation in Cost of Borrowing -35 -27 6 -26 -48 Interest 12 198 57 -22 -23 Other -11 -8 -11 -9 -11 183 344 321 168 -79 Funding Extra Spending adjustments required 95 1,066 Council Tax - Tax base adjustments 21 22 0 -24 0 Use of Reserves 162 322 321 97 -1,145 183 344 321 168 -79
3.8As can be seen from the funding lines in the table above, reserves will have to be used sooner and thus spending adjustments will also have to be identified and introduced earlier than previously forecast. The table below shows the acceleration in the use of reserves:
USE OF RESERVES 2009/10 2010/11 2011/12 2012/13 2013/14 £000 £000 £000 £000 £000 Approved Budget/MTP (February 2008) 2,599 3,874 3,741 2,944 1,358 Draft (November 2008) 3,596 4,631 4,063 2,902 1,145 Proposed in this report 3,758 4,952 4,385 2,999 0
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Strategy, Medium Term Plan and BudgetReport | 407 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.