Overview and Scrutiny Panel (Service Delivery): 2006-09 - transferred to Social Well-Being noted this item on Tuesday 7 April 2009. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Cabinet be recommended to (a) note the progress of the scheme and the results of the consultation to date; (b) defer the project and review the scheme in 12 months to allow time for the production of a scheme which more adequately suits the requirements of the Town; and (c) seek financial contributions towards the cost of the scheme from the County and St Ives Town Councils.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Service Delivery): 2006-09 - transferred to Social Well-Being
OVERVIEW AND SCRUTINY 7 APRIL 2009 (SERVICE DELIVERY)
CABINET 23 APRIL 2009
ENVIRONMENTAL IMPROVEMENTS TO ST IVES TOWN CENTRE (Report by Head of Environmental Management,)
1. INTRODUCTION
1.1St Ives Town Centre has been identified as being an area that required improvements due to its importance as a Town Centre area. There is a MTP scheme for £1080k in the programme to carry out these works between 2008 and 2010. A previous phase carried out improvements to the Bridge Street area. Phase 2 of the work is looking to improvements in the Market Hill area of the town centre. The whole purpose of the scheme is to ensure the continued economic prosperity of the town for future years by keeping it at a high standard of appearance and increasing footfall and reducing town centre traffic.
1.2This report outlines the progress to date and the process required to take the scheme forward to construction
2. SUPPORTING/BACKGROUND INFORMATION
2.1A previous phase was carried out in 2001 following wide consultation in the Bridge Street / Crown Street area.
2.2As part of the previous consultation, it was agreed that the second phase would be the Market Hill area. The district council supported this by including future monies in the capital programme.
2.3Following the guidelines set by Cabinet, an Advisory Group has been set up for the scheme. This includes the local District and County Councillors, Town Council representatives, Scrutiny representatives and representatives from local consultative groups such as the Town Centre Initiative, Access Group and Civic Society. Meetings have been held since May 2006 with these groups to discuss the principle of the scheme and, more recently, detail of the design.
3. MARKET HILL ISSUES AND PROPOSALS
3.1Market Hill, a large market square, regularly hosts a number of markets, including a charter market every Monday which takes over most of the space with stalls. There are safety issues with the present layout which could be improved with a new market layout.
3.2Currently, the pavements are narrow for a town centre and, with stalls erected on them, this causes restrictions to pedestrian flow. Traffic surveys have shown that vehicles will often drive around market place looking for spaces rather than go direct to the off street car parks, where there is extensive parking provision.
3.3The present layout of Market Hill has limited clear public open space and favours vehicles over pedestrians. Studies of semi-pedestrianisation of town centres have shown that this increase in pedestrian rights benefits both the economic vitality of towns and enhances the environment for shoppers. A St Ives specific study of the economy has not been carried out to assess the effect on varying degrees of pedestrianisation of the town. Several options were developed under the framework of the Advisory Groups over the last two years. These showed a range of options from slight reduction in parking provision, to minimum parking with maximum pedestrianisation. Total pedestrianisation is not possible as there is one road and several accesses off the square which need to be kept available at all times.
3.4The Advisory group agreed in autumn 2008 to take 3 options out to consultation. These options were;
Option1: a semi-pedestrianised scheme with the creation of a defined public open space outside three of the towns most notable buildings – the Free Church, Golden Lion and the Town Hall. A combination of Blue Badge / Public parking / loading is provided at the eastern end of the town centre. The scheme also proposed to move the War Memorial and Cromwell Statue into more prominent places in the open spaces.
Option 2: this has a similar road layout to Option 1 but provides extra parking for Blue Badge holders and delivery areas at the west end of Market Hill.
Option 3 is not to carry out any road layout changes, but just to enhance the existing street furniture, signage and surfacing.
3.5The plans included in Annex A show the three options that went out for consultation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Service Delivery): 2006-09 - transferred to Social Well-Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.