Noted progress of Phase 2 of the St. Ives Environmental Improvements Scheme; approved the principle of the scheme for the purpose of public consultation and its submission to the Huntingdonshire Traffic Area Joint Committee for approval; agreed to seek financial contributions towards the cost of the scheme from Cambridgeshire County Council and St Ives Town Council; and requested that a further report on the scheme’s progress be submitted to a future meeting.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
OVERVIEW AND SCRUTINY (SERVICE 2 SEPTEMBER 2008 DELIVERY)
CABINET 4 SEPTEMBER 2008
ENVIRONMENTAL IMPROVEMENTS TO ST IVES TOWN CENTRE (Report by Head of Environmental Management,)
1. INTRODUCTION
1.1St Ives Town Centre has been identified as being an area that required improvements due to its importance as a Town Centre area. There is a MTP scheme for £1080k in the programme to carry out these works between 2008 and 2010. A previous phase carried out improvements to the Bridge Street area. Phase 2 of the work is looking to improvements in the Market Hill area of the town centre. It is important to ensure that the town centre’s viability remains and this would be helped by keeping the centre’s appearance at a high standard as this scheme proposes.
1.2This report outlines the progress to date and the process required to take the scheme forward to construction and to get Cabinet’s permission to take the consultation forward.
1.3In September 2006, the Huntingdonshire Traffic Management Area Joint Committee was presented with a 116 signature petition which asked that, to enable the use of Bridge Street for Pavement cafes, the Committee vary the road traffic regulation order to prohibit loading after 10am daily. Preliminary consultation showed that there was a range of views on this proposal, and formal consultation was requested on the matter. It is intended that this consultation be included with the Market Hill proposals as they are related.
2. SUPPORTING/BACKGROUND INFORMATION
2.1A previous phase was carried out in 2001 following wide consultation in the Bridge Street / Crown Street area. This removed the parking from the street and replaced it with loading bays and disabled parking. The surfacing was changed to yorkstone pavements and gravel finished asphalt on the road. Despite early concerns over the design, compliments have been made about the final appearance.
2.2As part of the previous consultation, it was agreed that the second phase would be the Market Hill area. The district council supported this by including future monies in the capital programme.
2.3Following the guidelines set by Cabinet, an Advisory Group has been set up for the scheme. This includes the local District and County Councillors, Town Council representatives, Scrutiny representatives and representatives from local consultative groups such as the Town Centre Initiative, Access Group and Civic Society. Meetings have been held since May 2006 with these groups to discuss the principle of the scheme and, more recently, detail of the design. 3. MARKET HILL PROPOSALS
3.1Market Hill, a large market square, has a charter market every Monday which takes over most of the space with stalls. On Fridays there is a smaller market, with Farmers Market held fortnightly on Saturdays. There is charged parking (20 spaces) in the centre of the square with free parking on one side of the square. On Mondays, no parking is available within the square.
3.2The pavements are narrow for a town centre and, with stalls erected on them, this causes restrictions to pedestrian flow. Cars will often drive around market place looking for spaces rather than go direct to the off street car parks.
3.3Several options were drawn up and presented to the Advisory Groups over the last two years. These showed a range of options from slight reduction in parking provision, to minimum parking with maximum pedestrianisation. Total pedestrianisation is not possible as there is one road and several accesses off the square which need to be kept available at all times.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.