Noted the findings of the Overview and Scrutiny (Environmental Well-Being) on the adoption of roads and sewers in Huntingdonshire. Approved the contents of a communications plan, subject to consultation with Anglian Water on the proposed approach. Requested the Scrutiny and Review Manager to formally write to the local branch of the Law Society to draw their attention to the issues identified by the Panel; Requested the Panel to revisit the study once the extent is known of the sewers not under the responsibility of Anglian Water and following the implementation of the Government initiative referred to in paragraph 4.10 of the report; and requested the Scrutiny and Review Manager to lobby the local government association to seek the strengthening of the powers of the Highways Authority with regard to the road adoption process.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
ADOPTION OF ROADS AND SEWERS (Report of the Overview and Scrutiny Panel (Environmental Well-Being))
1. INTRODUCTION
1.1This report contains the background to, the methodology used and the findings following completion of a study on the adoption of roads and sewers in Huntingdonshire.
1.2The decision to undertake the study followed discussions by the former Overview and Scrutiny Panel (Service Delivery) on problems being reported by residents concerning delays in completing adoptions of roads. It was acknowledged that this is a national problem. The Panel decided to establish a Working Group to investigate the processes and procedures involved with a view to improving the speed of the adoption process. There have been changes to the membership of the Working Group since its establishment, with the final membership being Councillors J D Ablewhite, [name removed], M F Shellens, J S Watt and P K Ursell. Former Councillor D A Giles was appointed on to the Working Group and assisted with the investigations until April 2008 and the late Councillor Mrs C A Godley also participated in the study during its initial stages.
1.3Councillor P K Ursell has declared a personal interest in the study by virtue of his employment with a local developer.
1.4Discussions have been held with relevant District Council Officers and the Working Group is grateful to them for the support provided during the course of their investigations. Further details appear in section 3.
2. AIMS OF THE STUDY
2.1It was originally decided to undertake a study on the process of adopting estate roads and sewers with an aim to put measures in place that could streamline the process and make the procedures more transparent, initially by investigating the feasibility and potential benefits of introducing a District-wide register of unadopted roads and sewers.
2.2Having investigated the feasibility and utility of introducing a register of unadopted roads and sewers in the District, it has been concluded that this would not be appropriate given that the County Council already has a statutory duty to maintain a register of adopted roads, a register of unadopted roads would very quickly become out of date as new developments were completed and that maintenance of a register would have resource implications for the District Council. Nevertheless, the importance of the principle that underlies such a register has been acknowledged but it has been decided that it would be more appropriate to focus on ensuring that the necessary procedures are in place so that roads and sewers are adopted as soon as they become eligible under the respective statutory procedures.
2.3In light of the above, comprehensive investigations have been undertaken into the existing processes and procedures for adoption, with a view to making recommendations to improve upon the current systems and practices, and into the wider implications of these procedures.
3. WORKING GROUP’S ACTIVITIES
3.1The Working Group has met on a number of occasions and has been assisted in their deliberations by Councillor Peter Bucknell in his capacity as Executive Councillor for Planning Strategy and Transport. The following District Council Officers have been interviewed:-
• [name removed] – Projects and Assets Manager • [name removed] – Communications and Marketing Manager • [name removed] – District Council’s Head of Planning Services • [name removed] – Land Charges Officer • [name removed] – Head of Law, Property & Governance • [name removed] – District Council’s Development Control Manager • [name removed] – Principal Building Control Officer
The Working Group has also spoken to [name removed] – Highways Development Control Manager, Cambridgeshire County Council.
3.2In addition to interviewing the above Officers, the Working Group has undertaken comprehensive research in connection with the following:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.