Noted the findings of E W Consultancy (EWC) Ltd on the long-term sustainable use of Huntingdon Town Hall. Accepted their key recommendations including the principle of transferring the ownership of the freehold of Huntingdon Town Hall to an appropriate Building Preservation Trust when a long term solution has been identified through a options appraisal and subject to appropriate arrangements for the surrender of the current lease; supported the suggestion by the Overview and Scrutiny Panel (Economic Well-Being) to investigate the possibility of transferring the building to Huntingdon Town Council in exchange for land currently owned by them and requested further reports addressing the above issues.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
OVERVIEW & SCRUTINY ENVIRONMENTAL WELL BEING 13TH OCTOBER 2009
OVERVIEW & SCRUTINY ECONOMIC WELL BEING 15TH OCTOBER 2009
CABINET 22ND OCTOBER 2009
HUNTINGDON TOWN HALL (Report by Director of Environmental and Community Services)
1. INTRODUCTION
1.1This report concerns the recommendations from an independent report, commissioned by the District Council, into the most effective way to find a viable future for Huntingdon Town Hall.
2. SUPPORTING/BACKGROUND INFORMATION
2.1Huntingdon Town Hall is a grade 2* listed building in the freehold ownership of the District Council, which holds, it in trust, for the ‘public good’ of the people of Huntingdon. The ground and first floor are held on three 999 year leases from 1840 by Her Majesty’s Court Service (HMCS), as successors to the County Council, from whom the service had been transferred on 1st April 2005. The second floor is occupied by the Town Council (HTC) since local government reorganisation in 1974, there is no formal lease in this respect.
2.2The responsibility for all the upkeep and maintenance of the entire exterior and interior of building lies with HMCS except for interior and windows of the second floor which lies with HTC. HMCS vacated the building in 2007 on completion of the new Combined Justice Centre on Walden Road. HTC use the building sporadically.
2.3Discussions between the District Council and the occupiers have been ongoing for some time to seek a practical and viable way forward to secure the fabric of this most important building and an appropriate use(s). To assist this process the District Council commissioned a report on the condition of the building in 2007. This report concluded that £855K worth of work (plus fees) would need to be undertaken over a four year period to put the building in good order and that further detailed reports were required on some aspects. This estimate however did not include any works necessary for a new use or compliance with the Disability Discrimination Act, including the installation of a lift. The District Council has also acted in its statutory capacity to chase urgent repairs under Listed Building legislation. 2.4 Earlier this year the District Council commissioned EW Consultancy Ltd (EWC) to undertake a review, liaise with a number of stakeholders including HTC and to recommend a way forward including appropriate project management arrangements. A copy of EWC’s report is appended and has been circulated widely to Councillors and relevant stakeholders.
3. IMPLICATIONS
3.1Given the long leases and current responsibility for maintenance the Council could decide to take no further action other than its statutory role as regulator, under Planning and Listed Building legislation. The current condition of the building, whilst by no means perfect is not critical and in this context a watching brief would suffice. Furthermore, the extent of necessary repairs and improvements required over the next few years means that to accept the surrender of the leases without a clear plan for the future of the building would lay the Council open to a considerable liability.
3.2In view of the importance of the building, the District Council has taken a more proactive approach which has resulted in the report referred to above.
3.3The EWC report concluded that: As the first stage in this work, the District Council needs to give consideration to this report and in particular to decide on:
• Its approach to the project in terms of its long term involvement; • Project management arrangements; • Involvement by other organisations; • Immediate Governance arrangements; • Support for the project sustainable long term uses; • Any financial support in the short and medium term – capital and revenue.
3.4The key recommendations of the EWC report are that the District Council:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.