RESOLVED (a) that recommendations (a) - (g) contained in the report now submitted be approved; and (b) that the working group of the Overview and Scrutiny Panel (Environmental Well-Being) be congratulated for the excellence of their report. (The Chairman announced that he proposed to admit the following urgent item in accordance with Section 100B (4) (b) of the Local Government Act 1972 given the need to authorise the Head of Law, Property and Governance to enter into a Section 106 Agreement for the development as the application was currently the subject of an appeal against non-determination.)
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Management Panel (Decommissioned 18/05/2016)
Background
2.1The Panel’s interest in the subject was prompted by anecdotal evidence from members of the public’s concern over the pre-decision planning process. The Panel acknowledged at the outset that planning can be a contentious subject with “winners and losers”. The views of the public therefore have to be tempered accordingly.
2.2It was decided that the review of the development management process should concentrate on the process leading to the determination of planning applications, rather than the decision making process itself or the merits of decisions. The working group decided to look at the practices and procedures from first enquiry by potential applicants to the preparation of an officer’s final report and recommendations, involving pre-application advice, public consultation, plans and amendments, duration of the process and other related matters.
3. EVIDENCE AND INVESTIGATIONS
3.1The working group carried out extensive consultation to ensure that any recommendations that it made would be evidence based as opposed to personal anecdotes and the views of parties aggrieved by a decision. The following investigations and enquiries were therefore made -
• A questionnaire to town and parish councils, given their role as statutory consultees and frequently raised comments about the planning process. This generated a healthy 58% completion rate, the results of which are summarised at Appendix A.
1 • A press release which was reported in the local media which generated a total of 17 replies from individuals expressing views and concerns about the planning process.
• A search of other local authority websites and personal enquiries with other authorities on their policy of charging for pre-planning advice.
• An interview with the Planning Services Manager (Development Management) on the Council’s current processes and performance.
• An interview with representatives of two local planning agents (both of whom are former employees of the Council’s Planning Division).
• An interview with two applicants for planning permission to obtain a personal perspective of the process.
• An interview with the Council’s Scrutiny Manager on complaints regarding the planning process that are dealt with locally under the Council’s feedback system and through the Local Government Ombudsman.
• A further interview with the Planning Services Manager accompanied by the Chairman of the Development Management Panel on the working group’s provisional findings.
3.2Having conducted their investigations the working group has found that the Council’s processes compare favourably with other authorities and there is no significant cause for concern. However development management decisions can have very personal consequences for individuals affected by them which can colour their perception of the process and the decisions themselves. In particular the working group found that:-
• a growing number of authorities charge for pre-planning application advice;
• although not legally required, the Council has a procedure of posting notification letters to households that may be affected by a proposed development;
• the Council is not obliged to accept amendments to applications once they have been submitted, although officers tend to be flexible providing this does not delay the determination of an application unduly;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Management Panel (Decommissioned 18/05/2016) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.