Resolved
RESOLVED that the Head of Law, Property and Governance be authorised to enter into such agreement as he considers appropriate in the event that the Secretary of State decides that proposed development at RAF Upwood is acceptable.
Development Management Panel (Decommissioned 18/05/2016) agreed this item on Monday 19 April 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Head of Law, Property and Governance be authorised to enter into such agreement as he considers appropriate in the event that the Secretary of State decides that proposed development at RAF Upwood is acceptable.
ANNEX
SECTION 106 ADVISORY GROUP
REPORT BY THE HEAD OF PLANNING SERVICES
DEMOLITION AND CLEARANCE OF REDUNDANT BUILDINGS, RECLAMATION AND REMEDIATION OF LAND AND REDEVELOPMENT FOR MIXED USES INCLUDING HOUSING (AT LEAST 650 UNITS), EMPLOYMENT (AT LEAST 10 HA), NEIGHBOURHOOD CENTRE AND OPEN SPACE. RAF UPWOOD, RAMSEY ROAD, BURY
Planning reference: - 0900342OUT
1. INTRODUCTION AND PURPOSE OF REPORT
1.1The purpose of this report is to seek Members’ views on the proposals for infrastructure and community related benefits which would be associated with this proposed development. The application is now the subject of an appeal against non-determination. At its meeting on 16th November 2009 Development Management Panel noted a report on the decision which the authority would have taken had it had the opportunity. The ten reasons for refusal which have formed the authority’s case are set out in Appendix 1 to this report. The inquiry was originally scheduled to take two weeks, the last week in January and first in February, but the complexity of the evidence has necessitated a third week and the inquiry is currently adjourned to 27th April.
1.2It is normal practice for draft planning conditions and, where necessary a planning obligation, to be discussed at public inquiries. This is without prejudice to the local planning authority’s case but it enables the authority and the appellant to have an input to them if the Inspector, or as in this case, the Secretary of State, is minded to allow the appeal and grant planning permission.
1.3On the basis of the original tight timetable for the inquiry the appellants were advised that there would be no opportunity for the terms of a planning obligation to be reported to the S106 Advisory Group and authorisation given by the Development Management Panel. Such reference would have been necessary for a S106 ‘agreement’ (i.e. a document to which both sides are party) of this magnitude under the terms of the Delegation Agreement. The only alternative was a ‘unilateral undertaking’ (i.e. an obligation offered by the appellants). As the Council is not a party to a unilateral undertaking it does not have to agree to it and so the Panel authorisation which could not be obtained in time was not required. As explained above the authority can still comment on whether or not it considers the terms of a unilateral obligation to be acceptable.
1.4In this case the obligation, whether agreed or unilateral, would cover a range of contributions. Some have been negotiated with the appellants but others are still under discussion and are central to the outstanding objections. The technical differences between the two forms of obligation are that a unilateral cannot oblige the Council to undertake certain actions and this can cause drafting complications. In particular a unilateral cannot make provision for independent arbitration on any matters in dispute in relation to the implementation of the obligation. The adjournment of the appeal now provides an opportunity for the terms of an agreement to be authorised by the Development Management Panel.
2 THE SITE AND APPLICATION
2.1As reported to Panel in November, the application relates to a main site of 69ha which is the majority of the former RAF Upwood’s barracks and technical areas and further land totalling 3.7ha in two outlying sites for the sewage treatment plant and surface water balancing pond. The main site is located on the northern side of Ramsey Road/Upwood Road. The sewage treatment works site is to the west, off Upwood Road, Ramsey Heights. The balancing pond site is to the south of Ramsey Road. The application site does not include the former married quarters housing on the Fairmead Estate; the hangars which are in separate industrial use; or the runways, where gliding will continue, perimeter tracks and dispersal areas which extend to a further 123ha.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RAF Upwood S 106 AG Report 12-04-101Report | 48 KB | DownloadRead as text |
PDF |
SECTION 106 APPLICATION: DEMOLITION AND CLEARANCE OF REDUNDANT BUILDINGS, RECLAMATION AND REMEDIATION OF LAND AND REDEVELOPMENT FOR MIXED USES INCLUDING HOUSING (AT LEAST 650 UNITS), EMPLOYMENT (AT LEAST 10 HA), NEIGHBOURHOOD CENTRE AND OPEN SPACE, RAF UPWOOD, RAMSEYReport | 19 KB | Download |
Follow Development Management Panel (Decommissioned 18/05/2016) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.