Contact Officer: A Roberts (01480) 388015 This page is intentionally left blank MANA A GIN NG PRO P OJEC CTS – a corrpora ate gu uide
Version 1 [Draft 4.0 0] Febbruary 2011 CONTENTS
Page
Foreword
Introduction 1
Project Management Process 2
Process Schematic 6
Process Overview 7
Benefits Realisation Plan 8
Project Plan 9
Risk Register 10
Issues Log 10
Definitions 11
Annex A: Project Overview 13 INTRODUCTION
Purpose To ensure that adequate arrangements are in place to allow projects to be completed, ensuring the delivery of their intended outcomes and the realisation of their forecast benefits.
Definitions of the terms used in this guide are provided at the end of this document.
Context Change is an essential if we are to achieve the Council’s financial strategy, maintain our standing as an excellent council and deliver continuous service improvement. To realise the full benefit of change it must be effectively managed and usually this will be achieved through one or more projects. Change must have realisable benefits for one or more stakeholder. Inevitably these will always include a financial component which may be improved performance at the same or additional cost, or the maintenance of existing performance at a reduced cost, or the reduction of costs to meet lower budgetary provision.
Essentials For a project to be successful it must have a clearly stated outcome and there must be clarity about – • the benefits that will delivered to stakeholders • the resources that will be used to achieve the outcome • the time in which the project will be delivered • the tasks that need to be completed • the risks to the satisfactory delivery of the project • the capturing of issues that may need to be considered as the project progresses • who is managing the project on a day-to-day basis • who has responsibility for decisions at key stages in the project • who has the authority to make changes to the project • when the project starts and when it has been closed
The Council must learn from the experience of the projects it undertakes and they must be reviewed after any change has bedded down to verify that the outcome
1 has been achieved and the forecast benefits have been realised.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROJECT MANAGEMENTReport | 1.4 MB | DownloadRead as text |
Follow Overview and Scrutiny Panel (Economic Well-Being) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Dec 2015 | Zero Based Budgeting Update: Preparation for the 2016/17 Budget and Medium Term Financial StrategyRESOLVED that the Cabinet be recommended to include the savings proposals contained in Appendix 1 to the report now s... | Decided | Open |
| 8 Dec 2015 | Customer service strategyRESOLVED that t he Cabinet be recommended to approve the revised Customer Service Strategy. | Approved | Open |
| 8 Dec 2015 | Corporate fraud and prosecution policyRESOLVED that the Cabinet be recommended to: · approve the Fraud Workplan ; · approve the revised Prosecution Policy,... | Approved | Open |
| 8 Dec 2015 | Procurement policyRESOLVED that the Cabinet be recommended to approve the Procurement Policy. | Approved | Open |
| 8 Dec 2015 | Reserves reviewRESOLVED that the Cabinet be recommended to: · approve the Reserves Strategy; · endorse the minimum level of reserves... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.