That: · Overview and Scrutiny processes be reviewed following the Scrutiny away day, to include improved tracking of Overview and Scrutiny recommendations, improved information in reports to encourage challenge, and better decision making and analysis of Members’ skills to make better use of individual Overview and Scrutiny Panel Members; · Project management guidance be amended to require original Business Cases to be kept live and linked from the definition section of the Project Initiation Document (PID); · A session with the Programme and Projects Manager be arranged to explain the purpose of this new role and what it will achieve; · Project updates be included in the quarterly performance reports to Overview and Scrutiny Panels; · A review by the Overview & Scrutiny (Economic Well-Being) Panel be arranged for 6 months’ time to review steps followed in delivering the In-Cab Technology project and other projects currently in the delivery stage, including their procurement processes, and to assess how well the highlight reports for these projects are working; · A review by Members of the Project Management Select Committee be arranged for 12 months’ time to review financial reporting on projects and the post-delivery stage.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
This report is intended to present the findings of the Project Management Select Committee and make recommendations to Cabinet and Senior Management Team on how project management can be further improved.
The Select Committee was held on 17th February 2015 and involved looking back at past projects (Huntingdon Multi-Storey Car Park and the redevelopment of One Leisure St Ives), a demonstration of the Council’s project management tools and three workshop sessions each focussed on different project phases. Members were also given a range of information on how projects should be managed and access to details of current and past projects.
Throughout the day, a range of issues were discussed and a number of recommendations were proposed. In summary, the Chairman considered that the Select Committee was able to offer reassurance to the Council on the general direction of the new management team with regards to project management.
Recommendation(s):
It is recommended that: Overview & Scrutiny processes be reviewed following the Scrutiny away day, to include improved tracking of Overview & Scrutiny recommendations, improved information in reports to encourage challenge and better decision making and analysis of Members’ skills to make better use of individual O&S Panel Members Project management guidance be amended to require original Business Cases to be kept live and linked from the definition section of the Project Initiation Document (PID) A session with the Programme and Projects Manager be arranged to explain the purpose of this new role and what it will achieve Project updates be included in the quarterly performance reports to O&S Panels A review by the Overview & Scrutiny (Economic Well-Being) Panel be arranged for 6 months’ time to review steps followed in delivering the In-Cab Technology project and other projects currently in the delivery stage, including their procurement processes, and to assess how well the highlight reports for these projects are working A review by Members of the Project Management Select Committee be arranged for 12 months’ time to review financial reporting on projects and the post-delivery stage. This page is intentionally left blank 1. BACKGROUND
1.1Following consideration of a project closedown report on the Multi-Storey Car Park in Huntingdon and the One Leisure St Ives Redevelopment by the Overview & Scrutiny (Economic Well-being) Panel in November 2014, it was determined that a Select Committee would be convened in February 2015 to review the Council’s new Project Management procedures.
1.2The Select Committee was held on 17th February 2015, with all members of the Overview & Scrutiny (Economic Well-being) Panel and three members from each of the other Overview & Scrutiny Panels invited to attend.
2. SCOPE OF THE REVIEW
2.1The Terms of Reference for the Select Committee were: To review the Council’s project management arrangements in the wake of the issues highlighted by the One Leisure St Ives and Huntingdon Multi- Storey Car Park Close Down Report. To test the robustness of the Council’s new project management toolkit and governance arrangements. To consider how lessons learned have been addressed. To determine any further improvements required.
3. METHODOLOGY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.