Resolved
noted the approved Capital Programme 2011/2012 and the consequential estimated revenue impact.
Cabinet noted this item on Thursday 19 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
noted the approved Capital Programme 2011/2012 and the consequential estimated revenue impact.
CABINET 19 January 2012
FINANCIAL MONITORING - CAPITAL PROGRAMME 2011/12 (Report by the Head of Financial Services)
1. PURPOSE 1.1 This report highlights the forecast variations from the 2011/12 Capital Programme approved in February 2011. It includes any member or officer decisions already taken in accordance with the Code of Financial Management.
2. MONITORING OF THE 2011/12 CAPITAL PROGRAMME 2.1 The Budget approved in February 2011 was £11.9m after allowing for provisions for schemes brought forward from 2010/11 and carried forward to 2012/13. Subsequent adjustments are summarised below:-
2011/12 Capital Expenditure Capital Programme Gross External Net Budget Contributions Budget £000 £000 £000 Approved Total Budget (February 2011) 15,366 3,433 11,933 Actual brought forward from 2010/11 6,284 5,189 1,095 Less provision -1,444 0 -1,444 20,206 8,622 11,584 Supplementary Estimate Disabled Facilities Grant 401 -148 549
Forecast Cost Variations (Annex A) -283 456 -739 Forecast Timing Changes (Annex B) -11,586 -5,070 -6,516 Revenue to Capital Variations 266 0 266
Current Forecast 9,004 3,860 5,144
2.2The revenue impact on the MTP of the 2010/11 outturn and subsequent variations is shown below.
3. SIGNIFICANT ITEMS 3.1 Disabled Facilities Grants Cabinet approved a supplementary estimate at its September meeting to ensure that no applications would need to be delayed because of budgetary constraints. The figures shown above are based on actual spending to date together with the latest forecast of what will be spent in the rest of the year. All of the remaining cases, currently in the pipeline, are being progressed with the expenditure for many of them expected to fall into the next financial year. The lower forecast is predominantly due to OT referrals having fallen by 20% since August.
3.2Cambridge Street Car Park, St Neots This has been rephased to 2012/13 pending an agreement on the provision and management of the car park proposed for a cinema on this site.
3.3PV Panel Installations This report excludes the proposed PV panel Invest to Save schemes at Eastfield House and other council properties pending submission to COMT of revised project appraisals and risk assessments. It may well prove that schemes with adequate pay-back can still be achieved due to lower panel costs. If this is the case there may still be capital expenditure on the Eastfield House scheme in the current year.
3.4VAT Partial Exemption The amount of VAT that cannot be claimed back due to exempt supplies has been rephased because of the timing changes to the relevant schemes.
3.5Revenue to Capital Transfer Where appropriate, such transfers will be undertaken as they provide a beneficial revenue impact.
4. REVENUE IMPACT 4.1 The revenue impact on the MTP of the 2010/11 outturn and subsequent variations is shown below.
Revenue Impact 2011/ 2012/ 2013/ 2014/ 2015/ 2012 2013 2014 2015 2016 £000 £000 £000 £000 £000 Timing Changes 2010/11 to 2011/12 12 0 0 0 0 Cost Variations -1 -18 -21 -24 -26 Timing Changes 2011/12 to 2012/13 -33 -144 0 0 0 Revenue/Capital Transfers -126 26 29 33 37 Revenue variations re timing changes -20 127 -77 -170 -211 TOTAL FORECAST VARIATION -168 -9 -69 -161 -200
Notes: This table uses a simplified basis for identifying the revenue impact of capital expenditure. Allowance has also been made for any revenue elements of the changes as identified in the relevant MTP bid proposals - some of these are not just due to rephasing with some significant extra income being identified on leisure schemes. More accurate calculations will be included in the final Budget/MTP in February.
5. RECOMMENDATIONS 5.1 It is RECOMMENDED that Cabinet note the contents of this report.
BACKGROUND PAPERS Capital programme and monitoring working papers. Previous Cabinet reports on capital expenditure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring: Capital Monitoring 2011/12Report | 79 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.