Agreed that further work be progressed with partners through the Huntingdon Strategic Partnership to develop the framework and draft business plan, to take forward the next stages required in the Governance process; requested the Head of Planning and Housing Strategy to liaise with the Heads of Finance and of Legal and Democratic Services to agree draft procedural and management protocols; and requested a further report to be submitted to the Cabinet as procedural and management protocols become clearer.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
2.1The Community Infrastructure Levy (CIL) is a mechanism, introduced by Government in 2010, to allow local planning authorities to seek to raise funds from development in order to pay for the infrastructure that is, or will be, needed as a result of new development.
2.2The Huntingdonshire CIL Charging Schedule 2012, which was approved and adopted by Cabinet and Council in April 2012 (Minute109 and Minute 70 refer respectively) is as follows:
Charge for development types CIL rate (per square metre) All development types unless stated otherwise in this table £85 (standard rate) All A Class Uses 500 sq m or less £40 All A Class Uses > 500 sq m £100 All Class C1 Uses £60 All Class C2 Uses £45 Health (D1) £65 Business (B1), General Industrial, Storage & Distribution (B2 £0 and B8), Community Uses (within D1 - except Health Uses (1)
- and D2), and Agricultural (1. Community uses are ones provided by the public, not-for-profit or charitable sectors)
2.3The CIL is based on the need to finance identified community infrastructure needs, and it is payable per net additional square metre of floorspace. The identified community infrastructure needs are contained within Draft Charging Schedule Infrastructure Project List, November 2011, which was submitted as evidence with the Draft CIL Charging Schedule and can also be viewed on the CIL Examination page of the HDC website.
2.4The CIL charge is payable on commencement of development and will be registered as a Land Charge until final payment, or beyond if relief granted. Further details on the administration processes of CIL can be found on the HDC website. 2.5 The CIL Charging Schedule is complementary to the Developer Contributions Supplementary Planning Document (SPD) which was approved by Cabinet in December 2011. The SPD and the CIL now operate in conjunction with each other.
2.6Affordable housing development, certain development by charities and a limited range of minor ancillary development are exempt from CIL. All new dwellings, irrespective of size, are liable to pay CIL. Domestic household extensions under 100 square metres of net additional floorspace are not liable for CIL. All other development is liable for CIL if 100 square metres or above and is charged on a scale of rates based on viability testing that has been carried out. The outcome of the viability testing means that some types of new development, such as new business space, are subject to a nil charge, whilst other types of new development, including all new dwellings (houses and flats), are subject to a viability tested charge.
3. PROPOSED GOVERNANCE ARRANGEMENTS
3.1Breaking the link between specific contributions and the delivery of specific related infrastructure provision, as is the case within existing S106 Agreements, whilst adding welcome flexibility to spending priorities presents a significant governance challenge. Clearly, it will be important to ensure that additional infrastructure capacity is timed to coincide with the expected delivery of new development in a particular area. The spending of CIL will therefore need to be carefully planned and managed. Given that even on the most optimistic assumptions of the availability of other sources of funding there is still very likely to be a significant funding gap, priorities will need to be agreed between the various infrastructure providers, although it will be the District Council which will be responsible for making the final decisions in this regard.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.