Report to Overview and Scrutiny Panel (Environmental Well-Being)
Summary
1.1The report at Annex A and the accompanying appendices inform the work done to date in respect of Recycling Cambridgeshire and Peterborough Waste Partnership (RECAP) jointly procuring a materials recycling facility (MRF) to manage and process all the recycling materials collected across Cambridgeshire and Peterborough. It is a common report being presented to all the partnership waste collection authorities.
1.2The joint procurement is based on all the participating partners signing up to the procurement and abiding by the outcome. If any partner decides not to then the procurement will not proceed. The recommendations in Section 10 of the report in Annex A seeks approval of;
• the joint procurement of bulking, sorting and onward processing/sale of recyclable materials; • agreement that Peterborough City Council leads the process for the Joint MRF procurement for a preferred supplier for services of bulking, sorting and onward processing/sale of recyclable materials, collaboratively with and on behalf of all RECAP partners; • the delegation of the final Invitation to Tender (ITT) to the Head of Operations in consultation with the Environment Portfolio holder; • the revised Partnership Charter and Governance, Schedule 2; and • for Peterborough City Council to appoint the preferred bidder on behalf of RECAP, following agreement with the other partners.
1.3The contract will eventually incorporate all the partners due to varying contract termination dates, but all partners will sign up to the new joint contract and the incorporation timetable which will provide guarantees to the appointed contractor. 2. BACKGROUND
2.1A working group consisting of officers from all the partners in RECAP were tasked with taking the partnership through a joint procurement for a MRF operator to take all the recyclate from the partners. The Project Initiation Document for that is attached as Appendix 2 to the report attached at Annex A.
2.2Currently the different authorities in RECAP have 3 different contracts with different MRFs for their recyclate. It is clear from the work of other waste partnerships that the procurement of joint MRF contracts does realise benefits from pooling the tonnage of the various partners. The current contracts run out at different times and as a consequence they would need to be assimilated at different times into the main contract.
2.3The partnership is also looking at the optimum design for waste collection in light of the Waste Framework directive which requires source separated recyclate. This is explained further in the paper attached at Annex A, Appendix 3.
2.4All the Cambridgeshire authorities apart from Peterborough agreed and signed a Partnership Agreement in 2011. As Peterborough is part of this joint procurement then the agreement needs to be revisited and updated to include the Governance arrangements for the contract and that is included as Schedule 2 to the updated Partnership Agreement.
2.5A soft marketing exercise is currently underway which is seeking industry views about the types of recyclate we collect and how we can seek to maximise the tonnage of recyclable material which is collectable in a cost effective way. Further to this we are asking how the amount of contamination can be reduced and as a consequence the amount of recyclate having to go to landfill which is a cost to the partners.
2.6To realise the maximum possible savings it will require all partners, apart from the County Council to be party to this contract and for it to be binding on the partners.
2.7The invitation to tender (ITT) stage of the procurement of the contract will require partners to agree the tender prior to it being sent out and it is proposed that this should be delegated to the Head of Operations in consultation with the Environment Portfolio Holder.
3. RISKS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Environmental Well-Being) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Overview and scrutiny panel structureRESOLVED a) that Option 2 as detailed in the report now submitted be endorsed as a new structure for the Overview and...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.