Authorised the Head of Operations, after consultation with the Executive Member for the Environment, to approve the Invitation to Tender document for the joint procurement of a Materials Recovery Facility service and requested additional information in the meantime on the risks involved.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
This report seeks to give further information to the report considered in September in respect of a joint procurement of a Materials Recovery Facility (MRF) services for the bulking, sorting and onwards processing/sale of recyclable materials.
The procurement is being carried out by the RECAP Waste Partnership on behalf of all the partners excluding Cambridgeshire County Council who have a separate contract for recyclate collected at their household waste recycling centres.
Currently all the partners have existing contracts which are set to expire at different times and a new contract will encompass all partners for when their current contracts expire. This Council currently has a partnership contract with Fenland DC and Cambridge City Council which expires at the end of November 2014.
The recommendation in the report is to to delegate the approval of the Intention to Tender (ITT) document, for the procurement of a MRF contract, to the Head of Operations in consultation with the Executive Member for the Environment.
Background
1.1The RECAP Waste partnership, as part of a whole system approach to waste across the county, including Peterborough, are seeking to jointly procure MRF services for the bulking, sorting and onwards processing/sale of recyclable materials. To that end a task group, of officers from all the partners, was set up earlier this year to co-ordinate the procurement.
1.2The advantage of jointly procuring this type of service is that the tonnage of recyclable materials will be much greater and enable better prices to be achieved than individual councils procuring the service themselves.
1.3The income which can be derived from recyclate is very much dependant on the risk which the client decides they wish to take. The high risk pproach is to pay a flat processing fee to the MRF provider and then sell all the recyclate on the open market. As the market for recyclates fluctuates considerably the income received will do the same. In this scenario the contractor accepts no risk and receives a guaranteed payment for the processing of the recyclate.
1.4The low risk approach is to receive a much lower guaranteed payment for the recyclate based on a basket price which is advertised monthly in, for instance the Recycling News. This option is not without risk as the guaranteed payment is normally on a scale corresponding to the basket price. This is the current situation in the present joint contract. If the basket price drops beyond a certain point then the partners would end up paying the contractor to process the recyclate and not get any income and this could be the full processing cost.
1.5The medium risk approach is to have say 50% of the recyclate on the guaranteed model with the other 50% being subjected to the open market value. In this way there will, unless the bottom drops out of the market be a guareanteed income to the partners but if prices are high then the partners will benefit from the extra income.
Financial implications
2.1This Council recycles approximately 19,000 tonnes/year and therefore obtaining the best price for the recyclate is important in assisting the Council in meeting its savings target. In the low risk option the income does fluctuate with the basket price in bands but the return is small compared with that being received by other councils. The trend for wholesale recycling prices has been on a steady increase over the last 5 years, but the demand from the Chinese market has reduced which has led to the current fall in market prices.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.