i. Notes the progress made against Key Activities and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C of the Officer’s report. ii. Notes the Council’s financial performance to the end of September, as detailed in the Financial Performance Monitoring Suite in Appendix D of the Officer’s report. iii. Approves the inclusion of a supplementary capital bid to the 2015/16 capital programme for an upgrade to the Capita payments system, as described in Appendix E of the Officer’s report.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The purpose of this report is to brief Members on progress against the Key Activities and Corporate Indicators listed in the Council’s Corporate Plan for 2015/16 for the period 1 July 2015 to 30 September 2015. The report also incorporates progress reporting for current projects being undertaken at the Council and details of financial performance on revenue and capital spend as at the end of September.
The Corporate Plan’s strategic priorities have been allocated to Overview and Scrutiny Panels as follows:
Social Well-being 1. Working with our communities Economic Well-being 1. A strong local economy 2. Ensuring we are a customer focused and service-led Council Environmental Well-being 1. Enable sustainable growth
Recommendations
Cabinet are recommended to consider and comment on progress made against Key Activities and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C.
Cabinet are recommended to consider and comment on the Council’s financial performance to the end of September, as detailed in the Financial Performance Monitoring Suite at Appendix D.
Cabinet are asked to approve the inclusion of a supplementary capital bid to the 2015/16 capital programme for an upgrade to the Capita payments system, as described in Appendix E. 1. PURPOSE
1.1The purpose of this report is to present performance management information on the Council’s Corporate Plan for 2015/16 and updates on current projects.
Background
2.1The Council’s Corporate Plan was adopted as a two-year plan in 2014, with an update approved in April 2015 setting out what the Council aims to achieve in addition to its core statutory services during 2015/16. The information in the summary at Appendix A and the performance report at Appendix B relates to the Key Actions and Corporate Indicators listed for 2015/16.
2.2As recommended by the Project Management Select Committee, project updates are now included in this performance report at Appendix C. There are currently 28 open, pending approval or pending closure projects logged on the HDC SharePoint site across various programmes. This report covers all of the Council’s current and pending projects, including all Capital Projects. Four Capital Projects have currently been approved for spend in 2015/16.
2.3This report also incorporates financial performance to the end of September. Performance is summarised in section 4 below and details are listed in the Financial Performance Monitoring Suite at Appendix D.
3. PERFORMANCE MANAGEMENT
3.1Members of the Overview and Scrutiny (Economic Well-being) Panel have an important role in the Council’s Performance Management Framework and a process of regular review of performance data has been established. The focus is on the strategic priorities and associated objectives to enable Scrutiny to maintain a strategic overview.
3.2Progress against Corporate Plan objectives is reported quarterly. The report at Appendix B includes performance data in the form of a narrative of achievement and a RAG (Red/Amber/Green) status against each Key Action in the Corporate Plan and results for each Corporate Indicator. Appendix C gives a breakdown of projects including the purpose of the project and comments from the Programme Office as to the current status of each project’s SharePoint site as part of the new governance arrangements.
3.3Performance Indicator data has been collected in accordance with standardised procedures. Targets for Corporate Indicators and target dates for Key Actions have been set by the relevant Head of Service, after discussion with the appropriate Portfolio Holder.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.