Resolved
RESOLVED that consideration of the application be deferred pending closure of the consultation on it and to enable Officers to undertake further work on the recommended conditions.
Development Management Committee deferred this item on Monday 20 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that consideration of the application be deferred pending closure of the consultation on it and to enable Officers to undertake further work on the recommended conditions.
DEVELOPMENT MANAGEMENT COMMITTEE 20 JUNE 2016
Case No: 16/00679/FUL (FULL PLANNING APPLICATION)
Proposal: NEW TEMPORARY SITE ACCESS FOR CONSTRUCTION TRAFFIC. THIS INCLUDES NO DIG HAUL ROAD, DROP KERB ACCESS VIA PUBLIC HIGHWAY, REMOVAL OF EXISTING HEDGE. FOR DURATION OF CONSTRUCTION WORKS.
Location: LAND AT FORMER GOLF COURSE HOUGHTON ROAD ST IVES PE27 6RN
Applicant: BARRATT HOMES NORTHAMPTON (FAO MR D WOOD)
Grid Ref: 530357 271983
Date of Registration: 01.04.2016
Parish: ST IVES
RECOMMENDATION - APPROVE
This application is reported to Panel because the recommendation is contrary to the views of St Ives Town Council and relates to a Strategic Site. It has also been called in by Cllr Fuller, ward member for St. Ives West.
1. DESCRIPTION OF SITE AND APPLICATION
1.1This application is for a new temporary access for construction traffic to gain access to the site known locally as St. Ives Golf Course. The wider site lies to the west of St. Ives town centre, to the south of the A1123 (Houghton Road) and currently is accessed via the adjacent residential development, Knights Way.
1.2The redevelopment of the golf course was approved on appeal [see GREEN PAPER], on the 16th December 2015. The approved application proposes 184 dwellings on the northern part of the land, extending approximately as far south as the former clubhouse, and a new ‘country park’ to the south. This is a ‘hybrid’ outline planning permission proposing two phases of residential development.
1.3For phase one, comprising 59 dwellings, details of all five matters (access, layout, appearance, scale and landscaping) were provided as part of application 1301895OUT and development can start once pre-commencement conditions have been discharged.
1.4For phase two, comprising 125 dwellings, details of access, layout, appearance and scale, but not landscaping, were submitted.
1.5Condition 18 requires the submission and approval of a Construction Method Statement (CEMP) prior to the commencement of development. Part (i) of that condition is a requirement to agree the points of access for construction traffic, however, as this temporary access is proposed onto a classified road, it also requires a planning application in its own right.
1.6The applicants, Barratts who are part of BDW homes (the appellants for the residential scheme) have proposed to create the temporary access to the north west of the wider site. The creation of the access will require the removal of part of the hedge and creation of a dropped kerb.
1.7On the 27th May, the applicants submitted information for consideration under condition 18 (Construction Management / Construction Traffic Management Plan - CEMP) of 1301895OUT. The CEMP was updated on the 3rd of June to clarify a number of matters, including that the new access will be for HGV’s while Knights Way will be used for smaller contractor vehicles.
1.8Large/Heavy will operate using this access Monday to Friday 09.30 – 14.30pm and have a gatesman to assist with ingress/egress of the site. No works permitted on Sundays or Bank Holidays. The supporting statement dated 3rd June sets out like likely vehicle movements associated with the new temporary access.
1.9On the 3rd of June the applicant also submitted amended plans to this application for consideration. They also submitted a number of additional plans. The plans are: * Amended site Location Plan * Construction Management Plan * Site Execution Plan * Proposed Temporary Access * Proposed Temporary Access Site Plan
1.10The application will be considered on the plans and information, as amended on the 3rd June.
2. NATIONAL GUIDANCE
2.1Paragraph 14 – The presumption in favour of sustainable development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New temporary site access for construction traffic. This includes no dig haul road, drop kerb access via public highway, removal of existing hedge. For duration of construction works: Land at Former Golf Course, Houghton Road, St Ives: 16/00679/FULReport | 4.7 MB | DownloadRead as text |
Follow Development Management Committee at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Appeal decisionsRESOLVED that the contents of the report be noted. | Noted | Open |
| 17 Aug 2026 | Appeal decisionsRESOLVED that the contents of the report be noted. | Noted | Open |
| 20 Jul 2026 | Application requiring reference to the development management committee - change of use of site to coach depot and workshop and erection of security fencing - wansford railway station, old great north road, stibbington, peterborough - 25/01775/fulRESOLVED that the application be not determined. | Decided | Open |
| 20 Jul 2026 | Appeal decisionsRESOLVED that the contents of the report be noted. | Noted | Open |
| 22 Jun 2026 | Appeal decisionsRESOLVED that the contents of the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.