RE:FIT PROGRAMME - ENERGY CONSERVATION MEASURES FOR ONE LEISURE SITES

Approved Executive 1 paper

Cabinet approved this item on Thursday 20 October 2016. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

i. To approve the signing of Call-off Contract 2 with an exclusion clause for One Leisure Huntingdon Dry-side and One Leisure St Neots , both to realise savings at sites unaffected by lease issues and to give time to resolve outstanding lease issues; and ii. Remove One Leisure Ramsey from the scope of the programme owing to a potential redevelopment of the Ramsey Abbey School site incorporating the possible creation of a new leisure facility.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Executive summary

1. Following the Cabinet decision to defer the commencement of the Re:Fit project until lease issues at One Leisure (OL) sites have been resolved, the programme has now been reviewed to address Member concerns.

2. This report presents a proposed way forward, which will mitigate the risk associated with the unsigned leases at OL St Neots and OL Huntingdon (Dry- side) and to alleviate the uncertainty over the possible redevelopment of OL Ramsey.

3. Following discussions, Bouygues Ltd have proposed that Call-Off Contract 2 is amended to include an exclusion clause designed to protect the Council against liability in the event of a lease not being signed.

4. Work on the sites affected by the leasing issues will not commence until after the lease has been agreed. The exclusion clause will be triggered if a lease is not in place by 1st March 2017, and the site will be excluded from the programme at no cost to the Council.

5. Such an exclusion clause will allow the Council to invest in the unaffected OL facilities and to start to accrue savings without committing to sites with an uncertain future.

6. Owing to a possible redevelopment of the Ramsey Abbey School site, it is recommended that OL Ramsey is removed from the scope of the Re:Fit programme.

7. Savings arising from the energy efficiency measures installed through the Re:Fit programme of £109,000 over the next 3 years are already included in the Medium Term Financial Strategy (MTFS). With the exclusion of Ramsey from the programme these savings will need to be realigned to reflect this and will reduce to £84,000.

8. The deadline for agreeing the Call-off Contract 2 without the Investment Grade Proposal needing to be renegotiated is 31st October 2016.

9. The deadline for activation of the exclusion clause is 1 March 2017, which allows time for the Council to implement new leases at the affected sites. This deadline has been agreed in consultation with Bouygues Ltd.

The Cabinet is

RECOMMENDED

 To approve the signing of Call-off Contract 2 with an exclusion clause for OL Huntingdon Dry-side and OL St Neots, both to realise savings at sites unaffected by lease issues and to give time to resolve outstanding lease issues.

 To remove OL Ramsey from the scope of the programme owing to a potential redevelopment of the Ramsey Abbey School site incorporating the possible creation of a new leisure facility. 1. PURPOSE OF THE REPORT

1.1This report details the review of the Re:Fit programme following deferment by the Cabinet while the situation surrounding the leases for the One Leisure (OL) sites is resolved.

1.2Discussions have been held with Bouygues Ltd to find a way to accommodate the issues surrounding the leases and to re-align the programme.

1.3Bouygues Ltd have proposed that the Call-off Contract 2, the contract covering the delivery of the energy conservation measures, contains an exclusion clause which will mean that if the leases have not been agreed for St Neots or Huntingdon Dry-side, by an agreed date, then these sites will be removed from the project entirely.

1.4The exclusion clause will protect the Council from investing in OL sites with an uncertain future.

1.5The proposed exclusion clause will allow the Council to progress with the Re:Fit project and to realise the savings which have been built into the Medium Term Financial Strategy for the One Leisure budget.

1.6In addition, it is recommended that OL Ramsey is removed from the programme in light of a possible redevelopment of the site to which would potentially allow for a new leisure facility.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RE:FIT PROGRAMME: ENERGY CONSERVATION MEASURES FOR ONE LEISURE SITESReport 350 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
RB
Councillor Robin Beatham HoweChair, present
RC
Councillor Robin Clive CarterMember, present
SC
Councillor Stephen CawleyMember, present
RH
Councillor Roger HarrisonMember, present
JA
Councillor Jonathan Alexander GrayMember, apologies
DM
Councillor Darren Marcus TysoeMember, present
GJ
Councillor Graham John BullMember, present
SC
Councillor Steve CriswellMember, present
DB
Councillor Daryl BrownMember, present
JM
Councillor John Michael PalmerMember, present

On this subject at Huntingdonshire

Search all
  1. RE:FIT PROGRAMME - ENERGY CONSERVATION MEASURES FOR ONE LEISURE SITESThis decision
  2. Re:fit programme - energy conservation measures for one leisureDeferred
  3. Re:fit programme - energy conservation measures for one leisureDecided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open