i. Note the update report and progress; ii. Endorse the re-profiled live date of 27 February 2016 to allow a longer period for additional communication with residents; and iii. That a project review and closure report be scheduled for June 2017 to allow the new service to bed in over a two month period.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
1. The reconfiguration of our refuse and recycling rounds aims to maximise efficiencies and reduce fuel usage whilst meeting waste collection needs and delivering good customer service.
2. This report provides an update on the project.
3. The revised rounds for all collection services are complete, crews assigned and the communications plan is now fully underway. Initial communication began in December with advance warning included on Christmas hangers that changes are being made to collection rounds and to look out for more information early in 2017.
4. Implementation is on target for February 2017 with a re-profiled start date of 27th February to allow for additional communications to residents.
Recommendation(s):
The Cabinet are asked to:
1. Note the update report and progress.
2. Endorse the re-profiled live date of 27th February to allow a longer period for additional communication with residents.
3. That a project review and closure report is scheduled for June 2017 to allow the new service to bed in over a two month period (there are no meetings in May 2017). 1. PURPOSE OF THE REPORT
1.1The report is an update on the Waste Service round reconfiguration project.
Background
2.1Waste collection rounds were last reviewed in 2011.
2.2There is a need to reconfigure our rounds to:
balance workloads that have changed due to positive changes in recycling habits balance workloads through housing developments completed and maintain customer service meet the new collection requirements of planned housing development in the next 2 to 3 years and maintain customer service reduce fuel usage through optimised routing
2.3The Council agreed a target cost reduction of £276,000 within the waste service in its Zero Based Budgeting process.
2.4The project started in May 2016 with an original implementation date of 21st November 2016. This was revised to 6th February 2017 (approved on 4th October) to take account of the additional time required to achieve accurate customer data and responses regarding assisted collection and second bin services. It was also the earliest date after the Christmas period, the annual peak of the refuse and recycling workload.
2.5The last update report on 4th October to Overview and Scrutiny Panel (Communities and Environment) confirmed that the project was on track to the revised implementation date. The full project progress report and highlight report were presented and endorsed.
3. PROGRESS REPORT
3.1Appendix 1 to this report contains the formal progress report schedule for the project and Appendix 2 the highlight report for the project. The sub-projects and their status are shown below:
Sub-projects Status Round risk assessments 100% complete Review of properties on a sack 100% complete collection Review of official assistance 100% complete customers Review of farms and lodges 100% complete collections Review of properties with an 100% complete additional grey bin Review of a separate trade waste 100% complete collection round
3.2Since the last report to Overview and Scrutiny on October 4th, all work has been completed to plan including:
Assisted collections Second grey bin customers (including removal where customers are no longer eligible for the service) Full models of current collections Modelling of new collection rounds for household, recycling and green waste services Review and validation with waste management team and crews
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.