The Cabinet has received and noted progress made against Key Activities and Corporate Indicators in the Corporate Plan and current projects, as outlined in Appendix A and detailed in Appendices B and C of the report now submitted. The Cabinet has also noted the financial performance at the end of March 2020, as outlined in Appendix D and the register of reviews of Commercial Investment Strategy propositions as outlined in Appendix E of the report now submitted.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The purpose of this report is to brief Members on results at the end of the 2019/20 financial year for the Key Actions and Corporate Indicators listed in the Council’s Corporate Plan 2018/22 and progress on current projects being undertaken.
Key Actions, Corporate Indicators and targets are as included in the Corporate Plan Refresh 2019/20, as approved by Council on 24 July 2019.
The report also incorporates Financial Performance Monitoring Suite information setting out the financial position at 31 March 2020. It provides outturn figures for revenue and the capital programme. Headlines are:
Revenue – the forecast outturn shows underspend of £0.265m
Capital programme – the forecast outturn shows a net underspend of £2.814m
An update on the Commercial Investment Strategy includes details of investments to date and the level of returns these are expected to generate, with information on potential investment opportunities reviewed in Quarter 4 attached at Appendix E.
Recommendations
The Cabinet is invited to consider and comment on progress made against the Key Actions and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C.
The Cabinet is also invited to consider and comment on financial performance at the end of March, as detailed in Appendices D, and the register of reviews of Commercial Investment Strategy propositions at Appendix E. 1. PURPOSE
1.1The purpose of this report is to present details of delivery of the Corporate Plan 2018/22, and project delivery, in the context of the Council’s financial performance.
Background
2.1The Council’s Corporate Plan is currently being refreshed and once adopted will set out what the Council aims to achieve in addition to its core statutory services. The information in the summary at Appendix A relates to Key Actions and Corporate Indicators and the performance report at Appendix B details the year end results.
2.2As recommended by the Project Management Select Committee, updates for projects based on latest approved end dates are included at Appendix C. Across all programmes there are currently 16 projects which are open, pending approval or pending closure.
2.3This report also incorporates financial performance to the end of March. This performance was as shown in sections 4-6 below, with further details listed in Appendix D. Commercial investment propositions reviewed are at Appendix E.
3. PERFORMANCE MANAGEMENT
3.1Members of the Overview and Scrutiny (Performance and Growth) Panel have an important role in the Council’s Performance Management Framework and a process of regular review of performance data has been established. The focus is on the strategic priorities and associated objectives to enable Scrutiny to maintain a strategic overview. Their comments on performance in Quarter 4 will be published following their meeting on 8 July 2020.
3.2Progress against Corporate Plan objectives is reported quarterly. The report at Appendix B includes details of all Key Actions and Corporate Indicators at the end of Quarter 4. Appendix C provides information about projects, including the purpose of the project and comments from the Programme Office as to the current status of each project’s SharePoint site as part of the new governance arrangements.
3.3Performance Indicator data has been collected in accordance with standardised procedures.
3.4The following table summarises final outturn progress in delivering Key Actions for 2019/20:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.