The Cabinet has (a) noted the update on the A428 Black Cat to Caxton Gibbet Improvements Scheme Development Consent Order application to the Planning Inspectorate and the next stages and timescales in the process; (b) noted the emerging principles of concern identified from the technical analysis and provide member direction and comment on the key issues as outlined in paragraphs 5.1 and 5.2 of the report now submitted and any other areas for consideration; (c) confirmed the Council’s continued support of the A428 Scheme, subject to reaching agreement on identified issues with Highways England; (d) delegated authority to the Executive Leader and the Executive Councillor for Strategic Planning in consultation with the Managing Director and the Strategic Growth Manager to finalise the preparation and submission of the documents required from the Council as part of the legal Development Consent Order process, including the joint response with Cambridgeshire County Council and South Cambridgeshire District Council including the Local Impact Report, the Statement of Common Ground and Relevant and Written Representations.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Proposals have been submitted to upgrade the route between the Black Cat roundabout and Caxton Gibbet roundabout with a new 10-mile dual carriageway and a number of junction improvements. The scheme is one of the key investment programmes in the area. It will improve journey times for residents, businesses and visitors and support economic growth in the area between Milton Keynes and Cambridge as part of the wider aspirations of the Cambridge-Milton Keynes-Oxford (CaMkOx) Arc.
The Council has responded to three consultations on the proposed scheme to date: 2017 non- statutory consultation on preferred route options. This was reported to Cabinet on 20 April 2017 (Minute 98 refers). 2019 statutory consultation, following announcement of the preferred, providing outline detail on the route alignment, junction designs, routes for walkers, cyclists and horse riders and plans for environmental mitigation. This was reported to Members on 18 July 2019 (Minute 22 refers). 2020 statutory supplementary consultation outlining a number of changes to the development boundary and to the design of the scheme. This was approved by the Leader and Executive Councillor for Strategic Planning as technical matters only.
Details of the scheme and consultations held can be found on Highways England A428 website .
The Development Consent Order (DCO) was submitted by Highways England (HE) to the Planning Inspectorate (PINS) on 26th February 2021. All documentation in relation to the DCO can be viewed on the National Infrastructure Planning website . On 12th March 2021, the Council issued a response on the Adequacy of Consultation. This was approved by the Leader and Executive Councillor for Strategic Planning in consultation with the Corporate Director (Place) and the Strategic Growth Manager. The DCO application was formally accepted by PINS on the 23rd March 2021.
A briefing for members was held by Highways England on 24 March 2021 and a further round of engagement is anticipated. This report includes an update on the Council’s progress in negotiations with HE in our role as a Tier 1 Stakeholder and a statutory consultee in relation to the overall project. Recognising the strategic nature of this project throughout the process the Council has collaborated with Cambridgeshire County Council (CCC) in their role as the Local Highway Authority and South Cambridgeshire District Council (SCDC). There have been joint discussions relating to highway matters between Highways England, CCC, and the Bedford authorities.
The report outlines next steps and key milestones in the process. It notes the key issues identified to date from analysis of the information submitted and seeks member endorsement. Recognising this is a statutory process and may include the fixed timescales for formal Council responses on matters, such as but not limited to the Joint Local Impact Report (Joint LIR), it is recommended that authority is delegated to the Executive Leader and the Executive Councillor for Strategic Planning in consultation with the Managing Director and the Strategic Growth Manager. It is important to note that both the (Draft) Joint LIR and the (Draft) SoCG will remain continually evolving documents between now and during the Examination process as matters are negotiated as far as possible towards final agreement during the coming months.
RECOMMENDED
The Cabinet is recommended to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.