The Cabinet has considered and commented upon the progress made against the Key Actions and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C of the report now submitted.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The purpose of this report is to brief Members on progress against Key Actions and Corporate Indicators listed in the Council’s Corporate Plan 2018/22 for the period 1 July to 30 September 2021 and on projects being undertaken.
Key Actions, Corporate Indicators and targets are as included in the Corporate Plan Refresh 2021/22, as approved by Council on 21 July 2021.
The report does not incorporate the usual Financial Performance Monitoring Suite information setting out the financial position at the end of the Quarter. This information is being reported as a separate item to Overview and Scrutiny (Performance and Growth) Panel and Cabinet, due to the need for separate focus on financial matters as a result of the impact from Covid-19.
Recommendations
The Cabinet is invited to consider and comment on progress made against the Key Actions and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C. 1. PURPOSE
1.1The purpose of this report is to present details of delivery of the Corporate Plan 2018/22, and project delivery.
Background
2.1The Council’s Corporate Plan has recently been refreshed to reflect the impact of Covid-19 on services and was approved at the Council meeting on 21 July 2021. The performance data in this report and its appendices relates to the indicators and actions selected for 2021/22. The information in the summary at Appendix A relates to Key Actions and Corporate Indicators and the performance report at Appendix B details all results to the end of September.
2.2As recommended by the Project Management Select Committee, updates for projects based on latest approved end dates are included at Appendix C. Across all programmes there are currently 21 open projects.
3. PERFORMANCE MANAGEMENT
3.1Members of the Overview and Scrutiny (Performance and Growth) Panel have an important role in the Council’s Performance Management Framework and a process of regular review of performance data has been established. The focus is on the strategic priorities and associated objectives to enable Scrutiny to maintain a strategic overview. Their comments on performance in Quarter 2 will be inserted into section 4 of this report following the Overview and Scrutiny meeting on 3 November 2021.
3.2Progress against Corporate Plan objectives is reported quarterly. The report at Appendix B includes details of all Key Actions and Corporate Indicators at the end of Quarter 2. Appendix C provides information about projects, including the purpose of the project and commentary from the project managers as to the current status of each project.
3.3Performance Indicator data has been collected in accordance with standardised procedures.
3.4The following table summarises Quarter 2 progress in delivering Key Actions for 2021/22:
Status of Key Actions Number Percentage Green (on track) 18 72% Amber (within acceptable variance) 7 28% Red (behind schedule) 0 0% Awaiting progress update 0 0% Not applicable 0
Most key actions were on track at the end of Quarter 2 and none were significantly behind schedule. This is the same as at the end of Quarter 1 and an improvement on our year-end position for 2020/21 when multiple key actions were impacted by the Covid-19 pandemic and lockdown restrictions, which affected services’ ability to deliver and allocation of resources.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.