RESOLVED that the amendments to the Annual Governance Statement as outlined in Appendix A of the report now submitted be approved and that the Executive Leader and Managing Director be authorised to sign the Annual Governance Statement on behalf of the Council.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The Council is required by statute to produce an Annual Governance Statement (AGS, Appendix A).
Amendment has been made to the previously approved AGS to include an:
internal audit report & governance issue in respect of Contractor Management.
alternative heading of ‘Other Governance Issues We Have Identified’.
Amendments are highlighted in blue for easy reference. All other wording remains the same as the previously approved version.
Recommendation
Approve the amended Annual Governance Statement (Appendix A) and authorise the Executive Leader and Managing Director to sign the Statement on behalf of the Council. 1. PURPOSE OF THE REPORT
1.1To complete the processes for finalising and publishing the Council’s Annual Governance Statement (AGS) for 2020/21.
Background
2.1The Corporate Governance Committee is designated as ‘those charged with governance’ and consequently it is required to approve the AGS prior to publication by the statutory deadline 1st August.
3. APPROVE THE ANNUAL GOVERNANCE STATEMENT
3.1The Committee, on behalf of the Council, is required to review once a year the effectiveness of its system of internal control and following that review approve the AGS. The AGS will be published alongside the Annual Financial Report (AFR) and is shown at Appendix A.
The draft AGS was previously circulated to CGC members and was approved in July 2021.
An amendment is now required for the inclusion of the internal audit report for Contract Management (July 2021) and an additional governance issue arising from it. The internal audit report detailed 5 findings and actions (including 3 red rated ones) and highlights a governance issue. External auditors have stated that the AGS should be updated to reflect this.
3.2External Audit also advised that these issues be headed as ‘other governance issues identified’ and not significant governance issues, which relate to VRM issues.
3.3The amended version has been approved by our external auditors.
4. REASONS FOR THE RECOMMENDED DECISIONS
4.1The process that has been followed in preparing the AGS has been thorough and in line with statutory regulations.
4.2The issues that have been identified for inclusion within the AGS are referenced within the statement and are a reflection of the current situation.
5. LIST OF APPENDICES INCLUDED
Annex A – Annual Governance Statement 2020/21 (updated March 22)
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.