Huntingdonshire District Council
Corporate Governance Committee, Wednesday 17 June 2026 at 7.00pm

Corporate Risk Register

Noted Committee 4 papers

AI summaryHuntingdonshire Corporate Governance Committee noted the Corporate Risk Register covering resilience, fraud, data protection, staffing, transformation, safeguarding, EDI and local government reorganisation, and commented on progress.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted risks and management approach
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil, staff, residentsRisk management covers whole organisation

What was decided

The Committee noted the corporate risks to the organisation and whether they are being managed in line with the Risk Management Strategy.

The Committee commented on the appendix reports and on progress with risk management. Report 1.1

Why

Effective risk management is a critical part of the organisation's governance, identifying areas where the Council should take action to mitigate exposure and informing the annual Internal Audit plan. Report 2.1

Presenting the Risk Register to each meeting of the Committee is an integral part of the governance process set out in the Council's Risk Management Strategy. Report 2.2

What happens next

Fraud risk assessment final report and recommendations are due by June 2026, and a Corporate Fraud Team performance report is scheduled for the Committee on 8th July 2026. Report P15, P17

The draft Risk Management Strategy and Policy, updated by the new Risk Manager, will be presented to the Committee for consideration and approval. Report 5.1

Outstanding internal audit actions on cyber security are to be closed at the end of May and end of June 2026, and the Wellbeing action plan is on track to move to business as usual in August. Report P19, P20, P21

Implications

  • Risk: Resilience risk CORP0006 covers emergency planning, with work on Emergency Liaison Points in Brampton and reviews of Town and Parish emergency plans. Report P12, P13
  • Risk: Fraud risk CORP0009 shows approximately 25% of staff have completed online fraud awareness training, with actions in hand to increase uptake. Report P16
  • Risk: Staffing risk CORP0012 reports 34 Workforce Strategy actions completed, 11 in progress and 2 yet to start. Report P21
  • Risk: Data protection risk CORP0010 notes two cyber security internal audit actions still open pending full assurance, monitored by the Internal Audit team. Report P18
  • Risk: Local Government Reorganisation risk CORP0019 has 12 identified risks, each assigned to a designated owner and regularly reviewed. Report P25
  • Equalities: EDI risk CORP0018 reports a new quarterly EDI Group delivering outcomes such as a sign language awareness course and increased accessible parking. Report P24
  • Other: Safeguarding risk CORP0017 records that core safeguarding training has been completed by all eligible staff, with a new Members' safeguarding module being rolled out. Report P22, P23

Who and where

  • Council staff Report P16, P21, P22
  • Elected members Report P12, P23
  • Town and Parish Councils Report P12
  • Residents Report P12, P24

Timeline

  • Q1 2026: Resilience and Business Continuity work on emergency planning and BCP refresh. Report P12, P13
  • End of April 2026: Core safeguarding training completion deadline met for all eligible staff. Report P22
  • End of May 2026: Action 3703 on MFA and Single Sign-On to be closed. Report P20
  • June 2026: Fraud risk assessment final report and recommendations due. Report P15
  • End of June 2026: Action 3702 on processes to be closed. Report P19
  • 8th July 2026: Corporate Fraud Team performance report to Corporate Governance Committee. Report P17
  • August 2026: Wellbeing action plan to move to business as usual. Report P21

Plain English for the jargon

  • BAU: Business as Usual.
  • BCP: Business Continuity Plan.
  • EDI: Equality, Diversity and Inclusion.
  • ELP: Emergency Liaison Point, a location residents can access if they have to leave their homes during an incident.
  • HDC: Huntingdonshire District Council.
  • LGR: Local Government Reorganisation.
  • MFA: Multi-Factor Authentication.
  • T&P: Town and Parish (Councils).
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item71

Resolved

RESOLVED that the Committee commented on the reports in the appendices and progress with risk management and noted the risks to the organisation and whether they are being managed in line with the Risk Management Strategy.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Committee

Recommendations

1.1To comment on the reports in the appendices and progress with risk management.

Key Corporate Plan/Place Strategy Priorities

1 Effective risk management is a key aspect of ensuring that the Council is efficient and sustainable service delivery

Report Author(s)

Lydia Morrison – Corporate Director – Finance & Resources [email protected] 1. PURPOSE OF THE REPORT

1.1This report informs the Committee of the approach and work undertaken on the Corporate Risk Register including the latest heat maps relating to the corporate risks.

2. WHY IS THIS REPORT NECESSARY

2.1Effective Risk Management is a critical part of the organisation’s governance. The Corporate Risk Register identifies those areas where the Council should take action to mitigate its exposure and informs the annual plan for Internal Audit.

2.2Presenting the Risk Register to each meeting of the Committee is an integral part of the overall governance process as set out in the Council's Risk Management Strategy

3. BACKGROUND & CONTEXT

3.1A breakdown of the actions and/or activities that have taken place for the risks with targets has been provided below.

3.1.1 CORP0006 Resilience – Emergency Planning Response – Q1 2026 – Focus on awareness and support to elected members to ensure they understand their role during an incident and the support and communication they can expect from the Local Authority. HDC’s Community Resilience officer is working with several Town and Parish Councils to develop Emergency Liaison Points (ELPs). These will act as locations residents can access if they have to leave their homes during an incident. Brampton are due a dry ELP set up where other T&P leads will be invited to view the set up and the commitment from them. HDC are also offering to review T&P emergency plans to align with HDC incident response and improve communication pathways.

Business Continuity – Q1 2026 – BCP refresh and review currently underway with Heads of Service owning their priority areas and the response to ensuring the Council can deliver their essential services. The Emergency Planning team will be working around the priority areas and conducting desk top exercising to ensure the proposed response are appropriate and all considerations met at time of an incident.

3.1.2 CORP0008 Regulatory – The Council continues to keep a strategic watch on legislative developments through horizon scanning, Statutory Officer discussions, and regular meetings of both the internal Governance Board, relevant professional bodies, and the Senior Leadership Team. This will support timely updates to governance frameworks and ensure appropriate reporting to the Corporate Governance Committee. The effectiveness of these arrangements will be monitored on an ongoing basis.

3.1.3 CORP0009 Fraud – The planned programme of fraud, bribery and corruption risk assessment workshops are now complete. Progress has been good and there are now a significant number of fraud risks recorded within our Risk Management Software (4Risk), although there is follow-up work required for some teams in this area. The final report and recommendations are due by June 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register SummaryAppendix 1 97 KB Download
PDF
Risk Heat MapsAppendix 2 166 KB Download
PDF
Supplement: Key for Risk Heat MapsAppendix 2 129 KB Download
PDF
Corporate Risk RegisterReport 217 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
SC
Councillor Stephen ClaffeyMember, present
RC
Councillor Ryan CooganMember, apologies, sent representative
JA
Councillor Jonathan Alexander GrayVice-Chair, apologies, sent representative
PJ
Councillor Paul James Hodgson-JonesChair, present
RI
Councillor Ricky IoannidesMember, present as substitute
RM
Councillor Ross MartinVice-Chair, present as substitute
GS
Councillor Geoff SeeffMember, present
HT
Councillor Howard TobiasMember, apologies
PW
Philip Webb - Independent MemberMember, expected
MY
Councillor Mark YoungMember, present

On this subject at Huntingdonshire

Search all
  1. Corporate Risk RegisterThis decision
  2. Corporate Risk RegisterNoted
  3. Corporate Risk RegisterNoted
  4. Corporate Risk RegisterNoted
  5. Corporate risk registerDecided
  6. Corporate risk registerDecided

More from Huntingdonshire Corporate Governance Committee

All decisions
MeetingDecisionOutcome
17 Jun 2026 Approval for Publication of Draft 2025/26 Statement of AccountsRESOLVED that the Committee (1) considered and approved the Annual Governance Statement (Appendix 1); (2) considered ... Approved Open
17 Jun 2026 External Audit PlanRESOLVED that the Committee commented and noted the External Auditor’s Annual Planning Report, set out at Appendix 1. Noted Open
17 Jun 2026 Internal Audit Progress ReportRESOLVED that the Committee commented on and noted the update on work undertaken by Internal Audit to date. Noted Open
17 Jun 2026 Internal Audit Actions UpdateRESOLVED that the Committee commented on and noted the current position regarding actions arising from internal audit... Noted Open
17 Jun 2026 Internal Auditor's Annual Report - Including Head of Internal Audit Opinion 2025/26RESOLVED that the Committee noted, commented on and accepted the Annual internal audit report 2025/26. Noted Open