Report to Overview and Scrutiny Panel (Performance and Growth)
Executive summary
The Community Infrastructure Levy (CIL) is a planning charge, introduced by the Planning Act 2008 as a tool for local authorities in England and Wales to help deliver infrastructure to support the development of the area. It came into force on 6 April 2010 through the Community Infrastructure Levy Regulations 2010. Huntingdonshire District Council became a CIL charging authority in May 2012.
Local authorities must spend the levy on infrastructure needed to support the development of their area. This helps to deliver across several the Council’s Corporate Plan priorities for 2022/23 but specifically: • Improving housing provision. • work closely with towns and parishes to widen knowledge around the Community Infrastructure Levy and how local communities can access these funds.
The latest funding round was launched on 9th November 2022 with a closing date of 9th January 2023. Bids received within that round for CIL funding towards infrastructure projects have been assessed by officers to reach the recommendations within this report.
Recommendation(s):
The Cabinet is
RECOMMENDED
a) Note the information on projects previously allocated or in receipt of funding commitments and the updates on their delivery (see Appendix 1). b) Agree officer recommendations for projects submitted in this round for over £50,000 CIL funding as detailed in Section 4.
c) Agree change requests for St Ives Park Extension and St Neots Riverside projects (see Appendix 3) 1. PURPOSE OF THE REPORT
1.1The purpose of the report is to invite the Cabinet to consider recommendations relating to infrastructure projects seeking funding in whole or in part from an amount of the Community Infrastructure Levy (CIL) monies received to date.
2. WHY IS THIS REPORT NECESSARY/BACKGROUND
2.1The requirement for infrastructure to support new development is a high priority and CIL continues to be implemented across the country with government enabling and directing local authorities to obtain contributions by charging a Community Infrastructure Levy on new development, in addition to negotiating Section 106 planning obligations with a developer where applicable.
2.2Up to 5% of CIL receipts each financial year may be retained for administration costs. 15% - 25% of CIL receipts – the ‘meaningful proportion’ – are passed to parish/town councils in line with the CIL Regulations 2010 (as amended) and the Localism Act 2011 and the total amount transferred to parish/town councils has increased each year in line with receipt increases. The remaining 70-80%, the strategic proportion, is available for Huntingdonshire District Council as the charging authority to spend on the provision, improvement, replacement, operation, or maintenance of infrastructure to support the development of its area.
2.3An update on the projects allocated CIL funding previously can be found at Appendix 1.
2.4Under Cabinet approved governance arrangements, the Cabinet is to consider applications for CIL funding over £50,000. Any requests of £50,000 or less have been considered and approved in line with delegated authority and are detailed at Appendix 2. The total amount of funding to be considered for allocation in a financial year will not exceed £500,000 for allocations of £50,000 or less, including those for non-parished areas. This report relates to the second funding round for the 2022/23 financial year.
2.5Change requests have been received for the previously approved projects at St Ives Berman Park and St Neots Riverside Park, these are covered in full in Appendix 3. These are recommended for approval of the changes. 3. OPTIONS CONSIDERED/ANALYSIS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Performance and Growth) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.