AI summaryHuntingdonshire Cabinet approves £1,686,632.81 of Community Infrastructure Levy funding to five projects and declines one pavilion bid, with a next funding round opening 27 October 2025.
Written from the decision and the officer reportPDF Pro
OutcomeNotedOne approved at reduced amount
Money£1,686,632.81 of CIL approved in this roundOut of £1,930,115.66 requested
What happens nextNext CIL round opens 27 October 2025Decisions expected March 2026
Who it affectsApplicants, parish and town councils, residentsAcross Huntingdonshire district
What was decided
Cabinet approved CIL funding for the Huntingdon Campus Retrofit skills training facility (Cambridge Regional College), for a total project cost of £725,912.00 with a £200,000.00 CIL ask. Report 4.2, P50, P51, P54
Cabinet declined CIL funding for the Warner's Park Pavilion extension and refurbishment in St Ives, where the Town Council had requested £160,000.00 against a £177,399.00 project cost. Report P86, P87, P90
Cabinet approved a reduced CIL award of £61,632.81 for the Kimbolton and Stonely playgrounds, focusing on the Kimbolton Mandeville Hall site rather than the original £118,517.66 ask. Report 4.4, P116, P138
Cabinet approved CIL funding for a new full-size floodlit 3G pitch at HDC One Leisure St Ives (£300,000.00 CIL ask, £1,400,031.26 total project cost), the Cromwell Museum expansion in Huntingdon (up to £1,000,000.00 CIL ask, £6,308,000.00 total cost), and the King George V Pavilion redevelopment in Huntingdon (£125,000.00 CIL ask, £1,000,000.00 total cost). Report 4.5, 4.6, P141, P169, P192
Why
Projects were scored against the Cabinet-agreed Statement of Intent covering links to growth, Corporate Plan priorities, partnership working, match funding, and evidence of need; the Warner's Park Pavilion bid was declined because the supporting evidence did not show clear links to growth or current use. Report P39, P40, P107, P108, P109
Officers assessed Kimbolton and Stonely as two play areas being ambitious for the local under-15 population and recommended focusing CIL on the Kimbolton site with a reduced award. Report P137, P138
Cabinet also noted that this is the first CIL funding round for 2025/26, with circa £35m of CIL receipts still available for allocation against potential future strategic projects such as the A428, A141 and East West Rail. Report 2.5, 3.3, 3.9, P36, P37
What happens next
Applicants will be notified of the Cabinet outcome and given feedback; contracts will be prepared for approved projects once conditions are met and funds released against agreed milestones, with quarterly monitoring. Report 8.1, P235, P236
The next CIL funding round will open on 27th October and close on 19th December 2025, with decisions expected in March 2026. Report 3.10
A review of CIL governance is moving to its next phase and will link to the Infrastructure Delivery Strategy and Plan supporting the updated Local Plan, which is expected to be submitted to the Planning Inspectorate by December 2026. Report 2.8, 2.11
The money
£200,000.00 CIL ask approved for Huntingdon Campus Retrofit skills training facility (total project £725,912.00) Report 4.2, P50, P51
£160,000.00 CIL ask declined for Warner's Park Pavilion, St Ives (total project £177,399.00) Report P86, P87
£61,632.81 Reduced CIL award for Kimbolton and Stonely playgrounds (against £118,517.66 ask and £163,360.66 total project cost) Report 4.4, P115, P116, P138
£300,000.00 CIL ask approved for new 3G pitch at HDC One Leisure St Ives (total project £1,400,031.26) Report 4.5, P141
£1,000,000.00 CIL ask approved for Cromwell Museum expansion, Huntingdon (total project £6,308,000.00) Report 4.6, P169, P170
£125,000.00 CIL ask approved for King George V Pavilion redevelopment, Huntingdon (total project £1,000,000.00) Report P192, P193
£1,930,115.66 Total CIL funding requested across all submitted applications this round Report 5.11
£1,686,632.81 Total CIL funding recommended for approval across all submitted applications this round Report 5.11
circa £35m CIL receipts currently available for allocation on further infrastructure projects Report 3.9
circa £29.8m CIL previously allocated to 60 projects supporting over £106m of infrastructure Report 2.3
Options considered
Chosen: Approve Huntingdon Campus Retrofit skills training facility (Cambridge Regional College). Strong evidence of need, match funding of £330k from CPCA plus college funds, links to Corporate Plan and net zero skills gap Report 4.2, P77, P78, P79, P80, P81
Chosen: Decline Warner's Park Pavilion, St Ives extension and refurbishment. Supporting evidence did not show clear links to growth, current use or strategic need; statement of intent not met Report P107, P108, P109, P110
Chosen: Approve a lesser amount of £61,632.81 for Kimbolton and Stonely playgrounds. Two play areas considered ambitious for 250 under-15s; reduced award focused on the Kimbolton site, with conditions including match funding and a sinking fund Report 4.4, P137, P138, P139
Chosen: Approve new 3G pitch at HDC One Leisure St Ives. Evidence of shortage of 3G pitches linked to growth, identified as priority in Playing Pitch and Outdoor Sports Strategy Report 4.5, P159, P160, P163
Chosen: Approve up to £1,000,000.00 of CIL for Cromwell Museum expansion, Huntingdon. Strong links to town centre regeneration and Corporate Plan; phase 1 already fully funded; CIL ask is 15% of total project cost Report 4.6, P186, P187, P188
Chosen: Approve King George V Pavilion redevelopment, Huntingdon. Addresses loss of cricket provision and barriers to growth; 13% CIL ask; good match with Playing Pitch Strategy Report P208, P209, P210
Implications
Legal: CIL must be spent under Regulation 59 of the CIL Regulations 2010 on infrastructure to support development, and may not be used to fund affordable housing. Report 10.1, 10.3, 10.4, P244
Financial: Of the £1,930,115.66 requested this round, £1,686,632.81 was recommended for approval; circa £35m of CIL remains available for future allocations including potential strategic projects such as the A428, A141 and East West Rail. Report 3.3, 3.9, 5.11, P36, P37
Risk: If too much CIL is allocated to other projects, funding may not be available for larger strategic infrastructure projects expected to come forward in the next few years. Report 3.3
Staffing: Staff resources, partly funded by the 5% CIL administration allowance, are needed to administer and monitor allocations and to prepare bids across the council. Report 2.2, 10.2, 10.3
Other: Outcome of a CIL funding enquiry form launched in May 2025 is being considered; officers suggest making it mandatory for applications of £100,000.00 or less in future rounds. Report 2.12, 5.14
Who and where
Cambridge Regional College, as applicant for the Huntingdon Campus Retrofit training facility Report 4.2, P48
St Ives Town Council, as applicant for the declined Warner's Park Pavilion bid Report P84
Kimbolton and Stonely Parish Council, as applicant for the reduced playgrounds award Report 4.4, P113
HDC One Leisure St Ives, as applicant for the new 3G pitch Report 4.5, P141
The Cromwell Museum, as applicant for the expansion project Report 4.6, P167
Huntingdon Town Council, as applicant for the King George V Pavilion redevelopment Report P190
Town and parish councils across Huntingdonshire, who receive 15% to 25% of CIL receipts as the meaningful proportion Report 2.2
Timeline
May 2012: Huntingdonshire District Council became a CIL charging authority Report P1
June 2024: First stage of CIL governance review presented to Cabinet Report P6, 2.5
11th March 2025: Planning and Infrastructure Bill published and in House of Lords committee stage Report 2.9
April 2025: Cabinet made decisions on CIL funding using the interim guidance Report P6
2nd June 2025: Latest CIL funding round launched Report P6
15th August 2025: Closing date for the current CIL funding round Report P6
3rd October 2025: Delegated authority meeting considered CIL bids of £100,000.00 or less Report 2.5, 4.1
8th October 2025: Overview and Scrutiny Panel discussed this CIL allocation report Report 6.1
14th October 2025: Cabinet decisions taken on the projects listed in this report
27th October 2025: Start date for the next CIL funding round Report 3.10
19th December 2025: Closing date for the next CIL funding round Report 3.10
March 2026: Decisions expected on the next CIL funding round Report 3.10
December 2026: Updated Huntingdonshire Local Plan anticipated submission to the Planning Inspectorate Report 2.11
Plain English for the jargon
Community Infrastructure Levy (CIL): A planning charge that local authorities in England and Wales can levy on new development to fund infrastructure to support that development.
Strategic proportion: The 70-80% share of CIL receipts retained by the charging authority to spend on infrastructure to support growth, after the 5% administration allowance and the 15-25% meaningful proportion passed to town and parish councils.
Meaningful proportion: The 15% to 25% of CIL receipts passed to parish and town councils under the CIL Regulations 2010 and the Localism Act 2011.
Section 106: Planning obligations negotiated with a developer, separate from CIL, used to mitigate site-specific impacts of development.
Statement of Intent: The Cabinet-agreed principles used to assess CIL funding applications, covering growth links, Corporate Plan alignment, match funding, partnership working and evidence.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40
Resolved
The Cabinet has (1) noted the updates on delivery in relation to the projects previously allocated or in receipt of CIL funding commitments (see Appendix 1); (2) noted any new allocated CIL projects for £100,000.00 or less approved by delegation on 3 rd October 2025 (see Appendix 2 ); (3) agreed officer recommendations at Paragraph 4.2 to approvefunding for Huntingdon Campus Skills training facility; (4) agreed officer recommendations at Paragraph 4.3 to decline funding for Warner’s Park Pavilion, St Ives extension and refurbishment; (5) agreed officer recommendations at Paragraph 4.4 to approve a lesser amount offunding for Kimbolton and Stonely Playgrounds; (6) agreed officer recommendations at Paragraph 4.5 to approve funding for HDC One Leisure St Ives for a new 3G Pitch; (7) agreed officer recommendation at Paragraph 4.6 to approve funding for Cromwell Museum, Huntingdon expansion project; and (8) agreed officer recommendation at Paragraph 4.7 to approvefunding for King George V Pavilion, Huntingdon redevelopment .
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The Community Infrastructure Levy (CIL) is a planning charge, introduced by the Planning Act 2008 as a tool for local authorities in England and Wales to help them deliver the infrastructure needed to support development in their area. Huntingdonshire District Council (HDC) became a CIL charging authority in May 2012.
Local authorities must spend the levy on delivering infrastructure needed to support the development of their area through: • increasing the capacity of existing infrastructure or • repairing failing existing infrastructure, if that is necessary to support new development.
CIL helps to deliver across the priorities in the Council’s Corporate Plan 2023 - 2028 specifically Creating a better Huntingdonshire for future generations by:
➢ Improving housing - 24. Maintain the level of new housing delivery, which meets the needs of Huntingdonshire residents, including the type of home and tenure (open market and social housing).
➢ Forward-thinking economic growth - 39. Influence delivery of infrastructure including East West Rail, A428, A141 Strategic Outline Business Case and future Transport Strategies.
A review of CIL governance is continuing and the first stage was presented to Cabinet in June 2024. Following this an interim round of funding was opened at the request of Councillors, using the agreed Statement of Intent as a guide. At Cabinet in April 2025 decisions were made by Councillors using the interim guidance. The latest funding round was launched on 2nd June 2025 with a closing date of 15th August 2025, a window of 11 weeks for submission. Bids received within that round for CIL funding towards infrastructure projects have been assessed by officers to reach the recommendations within this report. The outcomes of this round do not preclude applicants from submitting applications to future rounds, and they will be considered against the adopted criteria at the time of determination.
Recommendation(s):
The Cabinet is
RECOMMENDED
a) Note the updates on delivery in relation to the projects previously allocated or in receipt of CIL funding commitments (see Appendix 1).
b) Note any new allocated CIL projects for £100,000.00 or less approved by delegation on 3rd October 2025 (see Appendix 2).
c) Agree officer recommendations at Paragraph 4.2 to APPROVE funding for Huntingdon Campus Skills training facility.
d) Agree officer recommendations at Paragraph 4.3 to DECLINE funding for Warner’s Park Pavilion, St Ives extension and refurbishment.
e) Agree officer recommendations at Paragraph 4.4 to APPROVE A LESSER AMOUNT of funding for Kimbolton and Stonely Playgrounds.
f) Agree officer recommendations at Paragraph 4.5 to APPROVE funding for HDC One Leisure St Ives for a new 3G Pitch.
g) Agree officer recommendation at Paragraph 4.6 to APPROVE funding for Cromwell Museum, Huntingdon expansion project.
h) Agree officer recommendation at Paragraph 4.7 to APPROVE funding for King George V Pavilion, Huntingdon redevelopment. PURPOSE OF THE REPORT
1.1The purpose of the report is to invite the Cabinet to consider recommendations relating to infrastructure projects seeking funding in whole or in part from an amount of the Community Infrastructure Levy (CIL) monies received to date.
WHY IS THIS REPORT NECESSARY/BACKGROUND
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.