Resolved
RESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when making a decision upon the recommendations contained within the report.
Overview and Scrutiny Panel (Performance and Growth) decided this item on Wednesday 7 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when making a decision upon the recommendations contained within the report.
This report provides the 2023/2024 Q1 update on the Market Towns Programme (MTP).
The MTP is an ambitious programme of economic led interventions to support Huntingdonshire’s town centres recover from the Covid-19 Pandemic, whilst also looking forward to renewing and reshaping our town centres and high streets in a way that promotes growth, improves experiences, and ensures sustainability in the future.
The MTP is funded through a combination of external funding from the Department for Levelling Up, Housing & Communities (DLUHC), Cambridgeshire and Peterborough Combined Authority (CPCA), Huntingdonshire District Council (HDC) Community Infrastructure Levy (CIL) and National Highways. This update particularly highlights:
Completion of final designs for the St Neots Market Square (Town Centre Improvements) and procurement of a contractor to deliver the scheme. Appointment of architects and technical advisers for the refurbishment of the Priory Centre, St Neots. Initiation of projects approved by the CPCA Board in March, concerning project delivery in St Neots, Huntingdon, and St Ives, in addition to the Ramsey Market Produce Hub project, funded via the Local Growth Fund. Completion of the Huntingdon, Ramsey, and St Ives masterplans.
RECOMMENDATION UPDATE
Cabinet is asked to:
Note progress regarding the projects (part of the Market Towns Programme) as highlighted above. PURPOSE OF THIS REPORT
1.1To provide an update on activity across the strands of the Market Town Programme.
UPDATE ON MARKET TOWNS PROGRAMME
ST NEOTS PROGRAMME:
Town Centre Improvements (Transport Projects)
2.1The final detailed designs for the Town Centre Improvements were completed during April. Considerable work has been undertaken to refine and improve the proposals over the last few months, factoring in feedback from residents and local stakeholders as part of both online and in person engagement activities. The final designs, which detail all the proposed works, are included within this link: Cabinet Submission
2.2The formal procurement process to appoint a contractor to undertake the scheme was commenced on the 2nd of May 2023, it will conclude during August 2023. A significant risk to the scheme has been a lack of interest from the market. As part of our early engagement, we have carried out market testing through the Eastern Highways Alliance Framework and have identified that a minimum of three contractors are expected to submit tenders. This is incredibly positive and will help to ensure a competitive and successful procurement process is completed.
2.3Every effort has been taken to mitigate risks. We have, for example, taken additional time to consider technical and cost challenges prior to the procurement process being launched. This has also included market testing with local contractors, to better understand how the work could be better phased, and the cost implications or benefits of this. Whilst this has extended the scheme schedule slightly, commencing construction in early Autumn, as opposed to late Summer, this additional work will be beneficial to the project on cost and delivery timescales.
2.4In terms of phasing and delivering the works within the Market Square, it is important that we ensure the operation of the Charter Market is maintained. This also includes other specialist Markets, for example, craft and farmers, and other events which are organised by St Neots Town Council. The Council is working with partners to maximise the operation of these Markets and events during the construction period and minimise disruption as far as possible.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
4. Market Towns Programme: Summer Update Appendix BAppendix | 4 MB | Download |
PDF |
4. Market Towns Programme: Summer Update ReportReport | 510 KB | DownloadRead as text |
PDF |
Market Towns Programme: Summer UpdateReport | 101 KB | Download |
Follow Overview and Scrutiny Panel (Performance and Growth) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Feb 2026 | CIL Governance - Phase 2 - Strategic AllocationRESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when makin... | Decided | Open |
| 21 Jan 2026 | Use of urgency provisionRESOLVED that the comments of the Report be noted. | Noted | Open |
| 21 Jan 2026 | Corporate peer challenge update 2025/2026 q3RESOLVED that the comments of the Overview and Scrutiny Panel be noted. | Noted | Open |
| 3 Sep 2025 | Corporate performance report 2025/26 (quarter 1)RESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when makin... | Decided | Open |
| 3 Sep 2025 | Local government outcomes framework initial consultation responseRESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when makin... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.