Cabinet, Tuesday 16 December 2025 at 7.00pm

Market Towns - Ramsey Update

Noted Executive 1 paper

AI summaryHuntingdonshire Cabinet noted progress on the Ramsey Great Whyte town centre improvement scheme, including Mews Close car park works starting January 2026 and main scheme works targeted for summer 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the report and proposed approach
Money£1,609,360 grant securedBalance £1,423,539, spend to date £185,821
What happens nextWorks start summer 2026Car park works January to February 2026
Who it affectsRamsey town centreResidents, businesses, shoppers and visitors

What was decided

Cabinet noted the contents of the report and the proposed approach to delivering improvements to Ramsey town centre, covering Mews Close car park upgrades, shop in a box units, and public realm enhancements. Report P1, P5

Why

The project aims to revitalise Ramsey high street, strengthen its character as the Gateway to the Fens, and deliver economic uplift, better pedestrian safety, and more retail choice through shop in a box units. Report 2.1, 2.3, 3.1

An original larger Market Produce Hub concept above the river culvert was found not feasible by Cambridgeshire County Council engineers, leading to a revised approach of smaller semi-permanent structures in a pedestrian environment. Report 6.2, 6.3

What happens next

Resurfacing and relining of Mews Close car park, including additional disabled bays, is to be carried out in January and February, phased so half the car park remains available. Report 5.1, 5.3

A Privately Financed Highways Initiative application submitted to Cambridgeshire County Council in June 2025 is progressing on a first come first served basis, with work now formally commenced. Report 6.6

HDC targets the commencement of main works in summer 2026, with full scheme use by November 2026, subject to highways and planning approvals and statutory consultation. Report 6.8, P42

The money

  • £1,153,525 CPCA Local Growth Fund grant secured Report P48
  • £295,000 CPCA Accelerated Funding (legacy) grant secured Report P48
  • £1,609,360 Total funding secured Report P48
  • £185,821 Total spend to date Report P48
  • £1,423,539 Total funding balance remaining Report P48
  • £58,652 CPCA Accelerated Funding spend to date Report P48

Options considered

  • Rejected: Larger Market Produce Hub structure over the river culvert. Not feasible due to weight restrictions and complexity of excavations above the culvert Report 6.2
  • Chosen: Smaller semi-permanent shop in a box units with improved pedestrian environment. Delivers original objectives while maximising deliverability Report 6.3
  • Rejected: Revised Mews Close car park layout. Decision made to retain the existing layout while optimising underused spaces for greater efficiency Report 5.2
  • Chosen: Improved Mews Close car park with resurfacing, relining and extra bays. To improve facility and add disabled bays Report 5.1

Implications

  • Financial: CPCA Accelerated Funding allocation must be spent within the current financial year; a change request has been submitted to extend Local Growth Fund use into 2026/27 but is not yet confirmed. Report 10.1, 10.2
  • Legal: A planning application will be required in parallel with the highway approval process, and legal services will be engaged as required. Report 6.4, 13.1
  • Risk: Project timetable has been extended by the need to wait for the first come first served PFHI process, which only formally commenced in December 2025. Report 6.6, 6.7, 6.8
  • Equalities: Disabled parking is to be retained and improved regardless of the final approach to general on street parking. Report 2.5, 5.1
  • Climate: Project aligns with the council's net carbon zero by 2040 commitment and adopts sustainable practices such as reusing over 100 sqm of block paving from St Neots Market Square at the Rivermill site. Report 8.4, 16.1, 16.8, P65
  • Staffing: The Regeneration Project team is currently fully resourced in staffing and budget terms to deliver this project. Report 14.1

Who and where

  • Residents of Ramsey Report 2.3, 4.1
  • Ramsey businesses and market traders Report 2.3, 4.1
  • Ramsey Town Council as project partner Report 2.4, 2.7
  • Shoppers and visitors to the town centre Report 3.1, P17
  • Disabled parking users Report 2.5, 5.1

Timeline

  • November 2022: Ramsey Visioning document approved by HDC Report P42
  • March 2024: LGF grant funding awarded by CPCA, formerly Market Produce Hub Report P42
  • September to October 2024: Public engagement and consultation held, over 300 responses Report 4.1, P42
  • March 2025: Detailed design work and scheme alterations submitted to Cambridgeshire County Council Highways Report P42
  • June 2025: Privately Financed Highways Initiative application submitted to Cambridgeshire County Council Report P42
  • July to November 2025: Project effectively paused until highways process commenced in December 2025 Report P42
  • December 2025: PFHI work formally commenced with Cambridgeshire County Council Report 6.6
  • January to February 2026: Mews Close car park resurfacing and relining works planned Report 5.3
  • Before March 2026: Rivermill improvements to be completed, including reinstated cast iron handrails and 150 sqm of new block paving Report 8.3, 8.4
  • February to June 2026: Planning and highways statutory consultation and approvals process Report P42
  • Summer 2026: HDC targets commencement of main Great Whyte works Report 6.8
  • November 2026: Scheme components in full use Report P42

Plain English for the jargon

  • PFHI: Privately Financed Highways Initiative, a Cambridgeshire County Council process for securing design input and approvals for works in the public highway
  • CPCA: Cambridgeshire and Peterborough Combined Authority, the funder of the Local Growth Fund and Accelerated Funding grants
  • LGF: Local Growth Fund, the main CPCA funding source for the project
  • UKSPF: UK Shared Prosperity Fund, used for the linked Ramsey retail support project and the Rivermill improvements
  • CPCA AF: CPCA Accelerated Funding, a legacy grant allocation to be spent within the current financial year
  • MTP: Market Towns Programme, the wider HDC programme of which Ramsey Great Whyte is a key element
  • HDC: Huntingdonshire District Council
  • CCC: Cambridgeshire County Council, acting as Highways Authority
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

The Cabinet has noted the contents of the report and the proposed approach to delivering improvements to Ramsey Town Centre.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Executive summary

This report updates Cabinet on progress towards delivering the Ramsey Great Whyte town centre improvement scheme. It focuses on three core areas: 1) improvements to the Mews Close car park; 2) the development of ‘shop in a box’ semi-permanent units to enhance retail choice and the town market; and 3) enhancements to the public realm, with particular emphasis on the pedestrian environment.

A brief update is also provided on the delivery of a separate project in Ramsey town centre, focused on improving the Rivermill location through the provision of a new accessible path to the canal, alongside the reinstatement of original cast-iron handrails and improved surfaces that reuse block paving previously in situ at St Neots Market Square.

Recommendation(s):

The Cabinet is asked to:

 Note the contents of the report and the proposed approach to delivering improvements to Ramsey town centre,

Purpose of the report

1.1To provide an update on activity to date and the next stages of project development and delivery.

2. INTRODUCTION

2.1The Ramsey Great Whyte project aims to revitalise Ramsey's high street by strengthening the town's unique character, celebrating its heritage as the 'Gateway to the Fens', and enhancing public spaces through improvements such as pedestrianisation and the introduction of new retail facilities. 2.2. The project builds on previous investment by HDC and partners. This includes the development of the new Civic Centre within the Great Whyte area itself, Digital Information screens, launched in the Summer, to promote local businesses, as well as provide information on the town’s heritage and culture. We have also provided funding to deliver community events and activities to Ramsey Town Council, and community organisations, with several activities for residents scheduled for Christmas this year.

2.3This initiative continues HDC’s approach to investing resources locally and aligns with the town's vision of becoming a prosperous market town with balanced growth, improved connectivity, and opportunities for residents and the wider community. Key benefits include economic uplift, better pedestrian safety, and more retail and service choice through the ‘shop in a box’ initiative.

2.4HDC has worked closely with Ramsey Town Council to develop project proposals, which include the potential pedestrianisation of a small part of the Great Whyte. This may result in the loss of a small number of on-street parking spaces, necessitating measures to mitigate any potential impact.

2.5It is important to emphasise that such changes are currently the suggested approach only and are subject to testing and approval by the Highways Authority. It is equally important to state that disabled parking is retained and in fact improved, regardless of the final approach to general on street parking.

2.6In relation to off-street car parking, HDC owns and manages the Mews Close car park. HDC has developed proposals to improve this car park. It will be resurfaced and relined with additional parking bays created through a more efficient layout.

2.7The Council also owns an adjacent undeveloped space, with potential for small-scale development. Ramsey Town Council (TC), a key project partner, has expressed interest in converting the undeveloped space into an additional car parking facility. This could mitigate on-street parking changes, improve local communications, and promote community empowerment. HDC is working with Ramsey Town Council to explore this and other options for the site. Any changes to the status and use of this site, however, would be subject to an options assessment, an appraisal and a decision making process independent of the Great Whyte project.

3. PROJECT CONTEXT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Market Towns: Ramsey UpdateReport 156 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
SJ
Councillor Sarah Joanne ConboyChair, present
LD
Councillor Lara Davenport-RayMember, present
SW
Councillor Stephen William FergusonMember, present
JE
Councillor Joanna Elizabeth HarveyMember, apologies
SA
Councillor Sally Ann HowellMember, present
JE
Councillor Julie Elizabeth KerrMember, present
BA
Councillor Brett Alistair MickelburghMember, present
TS
Councillor Tom SandersonVice-Chair, present as substitute
SW
Councillor Sam WakefordMember, apologies

On this subject at Huntingdonshire

Search all
  1. Market Towns - Ramsey UpdateThis decision
  2. Market towns programme - spring updateNoted
  3. Market towns programme - winter updateNoted
  4. Market towns programme summer updateApproved
  5. Market towns programme spring updateNoted
  6. Market towns programme - winter updateNoted

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies