The Cabinet has (a) authorised the Chief Planning Officer, in consultation with the Executive Leader and Executive Councillor for Economy, Regeneration and Housing, to prepare and submit formal comments on the current second non statutory consultation on the Fens and Lincs reservoirs and associated infrastructure proposals; and (b) delegated authority to the Chief Planning Officer to take all associated action necessary in the interests of the efficient and timely conduct of the Council’s compliance with the Fens Reservoir and the Lincs Reservoir Development Consent Order (DCO) procedures including but not limited to: i. prepare the Council’s responses to any written questions from Examining Authority during the DCO Examinations and to submit those to the Examining Authority; ii. settle the content of and submit any Written Representations to the Examining Authority; iii. to negotiate, settle and complete any legal agreements relevant to secure the granting of a DCO pursuant to the applications; iv. settling and the submission of the Statement of Common Ground to the Examining Authority; v. the instruction of witnesses and legal advisors throughout the Examination process if required; and vi. the discharge of DCO requirements made under any development consent order granted by Secretary of State.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Anglian Water, in partnership with Cambridge Water, is in the pre application stage of Development Consent Orders for Fens Reservoir and the Lincs Reservoir respectively, both with associated infrastructure requirements. Recognising the East of England as an area of high growth the reservoirs aim to secure a reliable supply of water for the future and create new opportunities for the region to thrive and grow.
In late 2022 a first phase of consultation on the sites identified was held and early concept designs.
The second phase of non-statutory consultation opened on 30th May and will close on 9th August 2024. This consultation outlines the preferred location of the associated water infrastructure needed for both reservoirs in order to fill them, treat the water and distribute the water to our homes and businesses.
Following this consultation there will be at least one further statutory consultation, likely mid- 2025, in line with the requirements of the Planning Act 2008, on the proposals prior to submission of the Development Consent Order (DCO) application.
The Council has been collaborating with a number of partners under the Fens Water Partnership in order to consider the potential development of the Fens Reservoir with an aim of creating a sustainable water resource for the area and future growth, whilst also enhancing the environment and wider social-economic opportunities for local communities. During the current round of consultation, a number of events have been held as identified on their website ( link in background papers)
Due to the statutory timings required, a short window of time is given in order for the consultation documentation to be considered and responded to by specialists across the council. As such it is not possible to prepare a draft response on this now or for a later Cabinet meeting. With that in mind, the proposal in this report is to seek authorisation for a response to be prepared with officers and authorisation to delegated to the Chief Planning Officer, in consultation with the Leader and Executive Councillor for Economy, Regeneration and Housing, to prepare and submit formal comments on the current second non statutory consultation on the Fens and Lincs reservoirs and associated infrastructure proposals.
Delegation is further sought on the next stages of work due to the statutory time constraints to respond to DCO matters incorporating a range of specialist support.
Recommendations
The Cabinet is
RECOMMENDED
1. to authorise the Chief Planning Officer, in consultation with the Leader and Executive Councillor for Economy, Regeneration and Housing, to prepare and submit formal comments on the current second non statutory consultation on the Fens and Lincs reservoirs and associated infrastructure proposals; and
2. to delegate authority to the Chief Planning Officer to take all associated action necessary in the interests of the efficient and timely conduct of the Council’s compliance with the Fens Reservoir and the Lincs Reservoir DCO procedures including but not limited to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.