Huntingdonshire District Council
Cabinet, Tuesday 18 November 2025 at 7.00pm

Transformation Framework

Approved Executive 6 papers

AI summaryHuntingdonshire Cabinet approves its approach to transformation for 2025/26, setting out six programmes, 31 major projects and 30 operational projects drawn from existing corporate and service plans, with the next annual update due in June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet endorsed the Transformation Framework for 2025/26
MoneyNo new moneyNo new resource implications from publication
What happens nextAnnual update in June 2026To be brought to Overview & Scrutiny Committee
Who it affectsCouncil services and residentsAll services across the district

What was decided

Cabinet approved the council's approach to transformation for 2025/26, set out in a single Transformation Framework that pulls together work from the Corporate Plan, change programmes and service plans. Report P11, 1.1, 1.2, 1.3, P42

The framework covers six programmes, 31 major projects and 30 operational projects, with 80 further continuous improvement activities noted but kept outside the 2025/26 delivery list. Report 1.1, 1.4, P42, P44

Officers confirmed there are no new resource implications, as the work is supported by the existing Medium Financial Plan. Report 8.1, 8.2, P72

Why

The LGA Corporate Peer Challenge in May 2024 recommended that the council define and communicate a single approach to transformation and continuous improvement. Report P3, 2.3, P22, P24, P25

An internal audit completed in August 2025 found good controls but advised a single, refreshed programme and project framework for consistent reporting, benefits realisation and project closure. Report P4, P26, P27

Officers see the framework as a tool to deliver Corporate Plan priorities and prepare the organisation for Local Government Reorganisation, with risks to be managed by prioritisation and governance. Report P5, P7, 5.1, 5.2, 5.3, 9.1, 9.2, 9.3

What happens next

An update will be taken to the Overview & Scrutiny Committee in June 2026, and the framework and supporting documents will be refreshed and published annually. Report P8, P46

The officer led Transformation Board will continue to approve, prioritise, evaluate or terminate activity, manage assurance, and trigger interventions where benefits, time, cost, risk or quality slip. Report P37, P38, P39, P40

A request from the Overview & Scrutiny Panel to consider renaming the document and bringing a fuller Transformation Plan back later was noted in the comments section of the report. Report 4.3, 4.5, 4.6, 4.11, 4.12, 4.13, P58, P59

Options considered

  • Chosen: Approve the approach to transformation as recommended. Recommended to bring all change and service improvement work into one clear framework and respond to LGA peer challenge advice. Report P9, P10, P11, 9.2, 9.3
  • Rejected: Rename the report (for example as a Project Tracker or Service Plan) and bring back a fuller Transformation Plan later. The Scrutiny Panel requested this, but the published decision wording only records approval of the approach; the request is logged in the comments for Cabinet to note. Report 4.5, 4.6, 4.13, P58, P59

Implications

  • Financial: No new resource implications arise from publishing the framework; the existing Medium Financial Plan supports the work. Report 8.1, 8.2, P72
  • Legal: Transformation Framework documents are not legally mandated but are encouraged to meet broader policy goals, funding criteria and public expectations. The council met the UK requirement to publish a Productivity Plan by July 2024, with no government requirement for 2025. Report 7.1, 7.2
  • Risk: Local Government Reorganisation may slow or pause some initiatives as programmes are realigned to the new unitary authority's priorities, and demand on the council will be managed through rigorous prioritisation and operational governance. Report P5, P7, 5.1, 5.2, 5.3
  • Staffing: Transformation resources are expected to shift toward supporting the transition to the new unitary authority, which may affect capacity to deliver planned change. Report P7, 5.2
  • Other: Annual publication and a June 2026 update to the Overview & Scrutiny Committee are intended to strengthen transparency and public assurance on transformation work. Report P8, P46

Who and where

  • Huntingdonshire District Council services delivering change and improvement projects Report 1.3, P42, 6.2
  • Residents and communities of Huntingdonshire, framed as the focus of service improvement and the Huntingdonshire Futures vision Report P2, 6.1, P19
  • Council staff, with attention to workforce, culture and readiness for the new unitary authority Report P31, P32, 5.1, 5.2
  • Future unitary authority that will inherit priorities, programmes and resources Report P5, P7, 5.1, 5.2

Timeline

  • 15 to 17 May 2024: LGA Corporate Peer Challenge took place and later recommended a clearer transformation framework. Report 2.3, P22, P24
  • July 2024: Council met the legal requirement to publish a Productivity Plan. Report 7.2
  • August 2025: Internal audit of transformation arrangements completed, confirming good controls and recommending a unified framework. Report P26, P27
  • 5 November 2025: Overview & Scrutiny (Performance & Growth) Panel considered the report and added comments for Cabinet. Report 4.1, 4.13
  • 18 November 2025: Cabinet decision to approve the approach to transformation.
  • 2025/26: Six programmes, 31 major projects and 30 operational projects to be delivered under the framework. Report 1.1, 1.3, P44
  • June 2026: Annual transformation update scheduled for the Overview & Scrutiny Committee. Report P8, P46

Plain English for the jargon

  • LGR: Local Government Reorganisation, the move to a new unitary authority in the area.
  • LGA: Local Government Association, the sector body that ran the Corporate Peer Challenge.
  • CPC: Corporate Peer Challenge, an LGA led review of a council's work and assurance.
  • HDC: Huntingdonshire District Council, the council making this decision.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

The Cabinet has approved the approach to Transformation.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Executive summary

This report presents the Council’s approach to Transformation for 2025/26, detailing the strategic change programmes, major change projects, and operational level transformation plans. It consolidates actions from the Corporate Plan, change programmes, and service plans into a single, focused Transformation Framework.

Our Council’s approach to Transformation is a commitment to continuously improving how the Council operates, placing residents and communities at the heart of service improvement, enhancing the district as a great place to live, work, study and visit, and working closely with partners to ensure services meet future needs. It is a crucial tool for delivering the Council’s Corporate Plan priorities and the Huntingdonshire Futures vision.

This document responds to the LGA Corporate Peer Challenge recommendation to define and communicate a clear transformation framework.

The Council has implemented the Transformation Framework with a robust governance structure including the officer-led Transformation Board, to oversee strategic delivery and assurance. An internal audit confirmed good controls in place regarding strategic alignment and decision-making, recommending a unified framework for consistent reporting and benefits realisation. The transformation activity is embedded across services and is actively monitored.

There is a risk that Local Government Reorganisation (LGR) may slow or pause some transformation initiatives the council is aiming to deliver. As the new unitary authority establish strategic direction, it may be necessary to realign programmes to reflect evolving priorities.

It should be noted that:

• Local Government Reorganisation (LGR): LGR may slow or pause some transformation initiatives as programmes are realigned to reflect the emerging priorities of the new unitary authority. Transformation resources will shift toward supporting the transition, presenting both constraints and opportunities for ongoing change.

• Scrutiny and Transparency: The framework and supporting documents will be refreshed and published annually, offering additional assurance on the work. An update will be brought to the Overview & Scrutiny committee in June 2026.

Recommendations

The Cabinet is

RECOMMENDED

1. To approve the approach to Transformation 1. PURPOSE OF THE REPORT

1.1To present the Council’s approach to Transformation with the framework, including the delivery of programmes and projects for 2025/26; which sets out six Programmes, 31 Major Projects and 30 Operational Projects.

1.2The Transformation Framework is not a new, additional piece of work, but a concise summary of the projects across the Council focussed on transformation and service improvement.

1.3The Transformation Framework includes projects that deliver on the objectives of the Corporate Plan, change programmes, and service plan projects classified as major or operational level projects.

1.4A series of 80 continuous improvement activities from across the council, underpinning service delivery and the successful implementation of transformational projects, were also identified through the service planning process. These have not been included in the Transformation delivery for 2025/26.

Background

2.1Corporate Strategic Planning Framework

The council has established a framework that forms the ‘golden thread’ from vision and desirable outcomes to objectives and then projects by which these are achieved. This is summarised in Appendix 1 and illustrated in the diagram below:

2.2Corporate Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
9. Appendix 1 Corporate Strategic Planning FrameworkAppendix 93 KB Download
PDF
9. Appendix 2: Transformation Delivery Programme by Corporate Plan PriorityAppendix 233 KB Download
PDF
9. Appendix 3: Transformation Framework and Summary for 202526Appendix 1.1 MB Download
PDF
9. Appendix 4 Transformation Delivery Programme by Service AreaAppendix 104 KB Download
PDF
9. Appendix 5 Transformation Delivery Programme list of programmes and projectsAppendix 557 KB Download
PDF
Transformation FrameworkReport 593 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
SJ
Councillor Sarah Joanne ConboyChair, present
LD
Councillor Lara Davenport-RayMember, present
SW
Councillor Stephen William FergusonMember, present
JE
Councillor Joanna Elizabeth HarveyMember, present
SA
Councillor Sally Ann HowellMember, present
JE
Councillor Julie Elizabeth KerrMember, present
BA
Councillor Brett Alistair MickelburghMember, present
TS
Councillor Tom SandersonVice-Chair, present
SW
Councillor Sam WakefordMember, present

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open