Corporate Risk Register

Noted Committee 3 papers

AI summaryHuntingdonshire Corporate Governance Committee noted the Corporate Risk Register and progress with risk management, with one change to the Transformation risk target score since the last report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee commented on appendices and progress
MoneyNot stated
What happens nextStrategy to return for approvalDraft Risk Management Strategy under review
Who it affectsRisk management across the CouncilUpdates across eight corporate risks and LGR

What was decided

The Committee commented on the reports in the appendices and progress with risk management. Report P4

It noted the risks to the organisation and whether they are being managed in line with the Risk Management Strategy. Report P4

Why

Effective risk management is a critical part of the organisation's governance and the Risk Register informs the annual plan for Internal Audit. Report 2.1

Presenting the register at each Committee meeting is an integral part of the overall governance process set out in the Risk Management Strategy. Report 2.2

The report allows the Committee to comment on and offer challenge to the Corporate Leadership Team as part of active risk management. Report P1

What happens next

The draft Risk Management Strategy and Policy will progress through governance stages before being presented to this Committee for consideration and approval. Report 4.1

Training on the 4Risk software continues to be rolled out across service areas to support effective risk logging. Report 4.2

Gold officer training is scheduled for January 2026, focused on legal responsibilities and strategic leadership. Report P13

Implications

  • Risk: The target likelihood for the Transformation risk (CORP0016) has been reduced from 3 to 2, giving a revised overall score of 6 (Medium). Report P11
  • Staffing: Risk Management is now provided by the Risk Team. Report 6.1
  • Staffing: Implementation of the Workforce Strategy is underway with full transition to business as usual targeted for August 2026. Report P16
  • Legal: Gold officer training in January 2026 will focus on the Council's legal responsibilities and strategic leadership duties. Report P13
  • Equalities: A new Equality, Diversity and Inclusion Group has been launched, expected to contribute to mitigating the staffing risk. Report P22
  • Other: Safeguarding training compliance: 60% on Level 2, 52.5% on Adults eLearning, 51.8% on Children eLearning, with reminders and manager escalation in place. Report P18, P19, P20, P21
  • Other: The Local Government Reorganisation risk register has been embedded into routine arrangements, with 12 identified risks allocated to named owners. Report P23

Who and where

  • Council staff required to complete safeguarding training Report P17, P18, P19, P20
  • Named owners of the 12 Local Government Reorganisation risks Report P23
  • Gold, Silver and Bronze resilience officers Report P13
  • The Council as a whole, given its exposure to the listed corporate risks Report 2.1

Timeline

  • October 2025: HDC supported a major incident, subsequent debrief completed and improvement actions being implemented. Report P13
  • November and December (recent): Seven fraud, bribery and corruption risk assessment workshops delivered to staff. Report P14
  • January 2026: Gold officer training scheduled on legal responsibilities and strategic leadership. Report P13
  • August 2026: Targeted date for full transition of the Workforce Strategy to business as usual. Report P16
  • 2025 to 2028: Period covered by the Fraud, Bribery and Corruption Strategy. Report P14

Plain English for the jargon

  • 4Risk: Software used for logging, consolidating and assessing risk data.
  • LGR: Local Government Reorganisation.
  • EDI: Equality, Diversity and Inclusion.
  • HDC: Huntingdonshire District Council.
  • Heat map: Visual tool showing residual risk scores across corporate risks.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item43

Resolved

RESOLVED that the Committee commented on the reports in the appendices and progress with risk management and noted the risks to the organisation and whether they are being managed in line with the Risk Management Strategy.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Committee

Executive summary

This report provides an update on the Corporate Risk Register and presents a heat map relating to the current residual risk scores and a summary report. It provides the Committee with the opportunity to comment on and offer challenge to the Corporate Leadership Team as part of the active management of risks.

The Committee is

RECOMMENDED

To comment on the reports in the appendices and progress with risk management. 1. PURPOSE OF THE REPORT

1.1This report informs the Committee of the approach and work undertaken on the Corporate Risk Register including the latest heat maps relating to the corporate risks.

2. WHY IS THIS REPORT NECESSARY

2.1Effective Risk Management is a critical part of the organisation’s governance. The Corporate Risk Register identifies those areas where the Council should take action to mitigate its exposure and informs the annual plan for Internal Audit.

2.2Presenting the Risk Register to each meeting of the Committee is an integral part of the overall governance process as set out in the Council's Risk Management Strategy.

3. CURRENT CORPORATE RISK REGISTER

3.1There has been one change to the Corporate Risk Register scoring since the last reporting period which is as follows:

3.1.1 CORP0016 Transformation - The target risk scores likelihood rating has been reduced from 3 to 2, resulting in a revised overall risk score of 6 (Medium) as seen in Appendix 1. This adjustment reflects the development and implementation of a comprehensive transformation framework, supported by a clearly defined governance structure. Further enhancements are in progress following the actions found in the internal audit report. Regular progress updates are being provided on actions.

3.2A breakdown of the actions and/or activities that have taken place for the risks with targets has been provided below:

3.2.1 CORP0006 Resilience - Training for Silver and Bronze officers has been completed, with activation arrangements now in place through the graduated response process. Gold officer training is scheduled for January 2026 focusing on the Councils’ legal responsibilities and strategic leadership duties. Business Continuity arrangements are subject to ongoing training, exercising and quarterly governance oversight. Desktop exercises will further strengthen response capability, with the likelihood rating to be reviewed as maturity increases. HDC supported a major incident in October 2025; a subsequent debrief has been completed and agreed improvement actions are now being implemented.

3.2.2 CORP0008 Regulatory – The Council continues to keep a strategic watch on legislative developments through horizon scanning, Statutory Officer discussions, and regular meetings of both the internal Governance Board and the Senior Leadership Team. This will support timely updates to governance frameworks and ensure appropriate reporting to the Corporate Governance Committee. The effectiveness of these arrangements will be monitored on an ongoing basis. 3.2.3 CORP0009 Fraud - Seven fraud, bribery and corruption risk assessment workshops have been delivered throughout November and December to equip staff with the knowledge and skills with identifying, assessing and treating fraud, bribery and corruption activities that could occur within their service areas. This forms part of the Anti-fraud, Bribery and Corruption Strategy 2025 -2028.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4. Appendix 1: Corporate Risk Register SummaryAppendix 255 KB Download
PDF
4. Appendix 2: Risk Heat MapsAppendix 147 KB Download
PDF
Corporate Risk RegisterReport 89 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
MJ
Councillor Michael John BurkeChair, present
BS
Councillor Barry Stephen ChapmanMember, apologies
JA
Councillor Jonathan Alexander GrayMember, apologies
PJ
Councillor Paul James Hodgson-JonesMember, present
AR
Councillor Andrew Rayner JenningsMember, present
RM
Councillor Ross MartinMember, present as substitute
DJ
Councillor Dave John ShawVice-Chair, present
IP
Councillor Ian Pele TaylorMember, present
PW
Philip Webb - Independent MemberMember, expected

On this subject at Huntingdonshire

Search all
  1. Corporate Risk RegisterThis decision
  2. Corporate Risk RegisterNoted
  3. Corporate Risk RegisterNoted
  4. Corporate Risk RegisterNoted
  5. Corporate risk registerDecided
  6. Corporate risk registerDecided

More from Huntingdonshire Corporate Governance Committee

All decisions
MeetingDecisionOutcome
17 Jun 2026 Approval for Publication of Draft 2025/26 Statement of AccountsRESOLVED that the Committee (1) considered and approved the Annual Governance Statement (Appendix 1); (2) considered ... Approved Open
17 Jun 2026 External Audit PlanRESOLVED that the Committee commented and noted the External Auditor’s Annual Planning Report, set out at Appendix 1. Noted Open
17 Jun 2026 Corporate Risk RegisterRESOLVED that the Committee commented on the reports in the appendices and progress with risk management and noted th... Noted Open
17 Jun 2026 Internal Audit Progress ReportRESOLVED that the Committee commented on and noted the update on work undertaken by Internal Audit to date. Noted Open
17 Jun 2026 Internal Audit Actions UpdateRESOLVED that the Committee commented on and noted the current position regarding actions arising from internal audit... Noted Open