PLANNING AND DEVELOPMENT CONTROL COMMITTEE 19th AUGUST 2015 REF. NO. PD/15/04
INFORMATION FOR COUNCILLORS
ADDRESS DETAILS 32 The Sandlings Prosecution package being prepared for failure to comply with Breach of Condition Notice. Planning application reference number IP/12/00815/VC Agreed that while a further application has been received from B & M Retail Ltd to vary the condition of the planning permission, that legal proceedings should be held in abeyance until the application has been determined.
Application has been withdrawn. Legal department instructed to proceed with prosecution for failure to comply with Breach of Condition Notice.
Further breach of condition notice served 8.7.2014, relating to condition which specifies items not to be sold. Notice to be complied with by 7.8.2014.
Store checked 7.8.2014, goods prohibited by planning permission are still being sold. However decision to continue with prosecution is being delayed until outcome of meeting between executive of B & M Stores and I.B.C has been determined.
Following discussion with Chief Executive, further application anticipated, therefore prosecution proceedings have been put on hold until an application is received and determined.
IP/14/00823/VC Further application received 30.9.2014 to vary condition of planning permission relating to sale of bulky goods. Proceedings held in abeyance until application is determined.
Officers in discussion with applicant, application to be referred to Committee May/June 2015.
Resolution to be resolved at Planning and Development meeting 3.6.2015 subject to a unilateral undertaking being agreed via Legal Department. Decision to be issued w/c 10.8.2015
Slade Street Car Park Star Lane Unauthorised installation of a fixed canopy, porta cabin building and metal container, application to retain canopy refused Planning application 2.4.2014. Enforcement notice served 28.5.2014 requiring the IP/14/00117/FUL canopy porta cabin and container to be removed by 30.9.2014.
Appeal against refusal of planning permission had been lodged and dismissed by Planning Inspectorate, compliance date had been held in abeyance. Compliance date is now 3 months from appeal decision date of 2.9.2014 i.e. by 2.12.2014.
IP/14/00825/FUL Further application received 1.10.2014 for the erection of a wooden pergola to replace existing canopy but in different position on site.
This does not affect or hold up enforcement notice already served. 1 PLANNING AND DEVELOPMENT CONTROL COMMITTEE 19th AUGUST 2015 REF. NO. PD/15/04
Planning permission for the wooden pergola refused by delegated decision.
Requirements of the enforcement notice should have been complied with by 2.12.2014. Applicant has advised officers that an appeal against the refusal of planning permission for the pergola is to be submitted. Enforcement action to be held in abeyance while this is being determined.
Awaiting submission of appeal if not received in near future will proceed with prosecution proceedings.
Appeal not submitted, final letter sent April 2015 pointing out that requirements of enforcement notice were now back in force and that the notice had to be complied with within 3 months of the date of the letter i.e. by 24.7.2015. Information received through agent that the canopy, container and porta-cabin building will be removed before end of compliance period. Awaiting compliance by 24.7.2015
Canopy removed, porta-cabin and container to follow shortly
Orwell Quay Service of Breach of Condition Notice requiring the works to be Planning permission carried out. IP/01/00927/FUL. Failure to comply with condition 11, Notice served 20.8.2014, requiring details of planned scheme to requiring portion of quay wall to be be submitted within 2 months of date of service and agreed repaired/replaced. scheme to be carried out within 6 months of agreement.
Scheme to repair quay wall received and agreed. Agreed scheme has to be carried out within 6 months from the date of agreement i.e. by 17.4.2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PD-15-05 Appeal Decision: 561 Bramford RoadDecisions | 178 KB | Download |
PDF |
PD-15-05 Delegated DecisionsDecisions | 182 KB | Download |
PDF |
PD/15/05 Information for CouncillorsReport | 340 KB | DownloadRead as text |
Follow Planning & Development Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. | Decided | Open |
| 29 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 29 Jul 2026 | PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. | Noted | Open |
| 1 Jul 2026 | Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. | Decided | Open |
| 1 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.