- that the Procurement Strategy set out at Appendix 1 of the report be agreed and the Head of Resource Management be authorised to take all necessary steps to implement it. Reason: To ensure that the Council has an up to date Procurement Strategy to support its corporate priorities
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
2.1The Procurement Strategy is part of a suite of procurement documents, and forms the bridge between the Council’s overall Strategic Priorities and the Contract Standing Orders. Contract Standing Orders are the rules by which goods, works and services are procured, and from which contractual arrangements are determined. The Procurement Strategy demonstrates how the Council can use its spending power to deliver wider corporate objectives, and to ensure that proper procedures are followed, so that all non-salary expenditure is governed by suitable contractual arrangements.
2.2The Council’s Procurement Strategy was last updated in October 2009. The 2009 Strategy focussed on three aims: - Efficiency and Effectiveness - Sustainability - Partnerships
2.3Many of the objectives within the 2009 Procurement Strategy have been achieved. Notable successes include the introduction of a fully e- enabled procurement process, and a full refresh of Contract Standing Orders to reflect changes in legislation. However, one of the key learning points arising from the implementation of the 2009 strategy is the need to ensure that the strategy and action plan is monitored and updated on a regular basis, in order to provide evidence of the progress being made, and to reflect the changing local government environment.
2.4The Strategic Themes contained within the new strategy are broadly similar to those within the 2009 Strategy. However, the actions associated with the Strategic Themes are targeted and specific, so that they can be set out clearly in the action plan.
2.5The Council historically spends in excess of £40m per annum externally on procuring goods, works and services, and needs to maximise the value from this expenditure.
2.6Capital Expenditure of approximately £21m per annum forms the most significant proportion of the Council’s spending on both Housing Revenue Account and General Fund projects. Other significant areas of expenditure are on Repairs and Maintenance, IT hardware and software, Telecommunications, Waste Disposal, and Artistes Fees. Alongside this is a wide variety of smaller spending, of different contracts ranging from swimming pool chemicals to weed-killing. 2.7 The variety of procurement required within a local authority environment requires a different strategic approach to that which exists in the private sector. It relies on a partnership between the procurement team, the service area experts, and the supplier to deliver the outcomes which the Council expects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.