Resolved
that the information for Councillors be noted.
Planning & Development Committee noted this item on Wednesday 24 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
that the information for Councillors be noted.
Development Management – Year-end Review: 2018/2019 1. Improving Planning Performance 1.1 In 2018 the government published revised information relating to planning performance targets for the Local Planning Authorities of England, which was pursuant to revisions made to the Town and Country Planning Act 1990 which sets particular criteria for when an LPA might be designated as under-performing. 1.2 A local planning authority can be designated only if, “the Secretary of State considers that there are respects in which the authority are not adequately performing their function of determining applications”
1.3The performance of local planning authorities (LPA) in determining major and non- major development will be assessed separately, meaning that an authority could be designated on the basis of its performance in determining applications for major development, applications for non-major development, or both. 1.4 The speed with which applications are dealt with measured by the proportion of applications that are dealt with within the statutory time or an agreed extended period; and, the quality of decisions made by local planning authorities measured by the proportion of decisions on applications that are subsequently overturned at appeal. 1.5 The designation thresholds are as follows.
Speed of major development within statutory or agreed timeframe - 60% Speed of non-major development within statutory or agreed timeframe - 70% Quality of major development decisions – those overturned at appeal – 10% of total decisions Quality of non-major development decisions – those overturned at appeal – 10% of total decisions Table 1 - Major Applications: January 2017 – December 2018
Local Authority (position No. of Major planning No. of planning nationally) applications determined applications determined within 13 weeks or agreed timeframe (%) Ipswich (19)* 66 66 (100%) Waveney (134) 53 49 (92.5%) Forest Heath (180) 46 41 (89.1%) Babergh (227) 90 77 (85.6%) St Edmundsbury (244) 75 63 (84%) Suffolk Coastal (295) 101 79 (78.2%) Mid Suffolk (297) 140 109 (77.9%) *Only 30 LPAs across the country achieved 100% Table 2 - Non-Major Applications: January 2017 – December 2018
Local Authority (position No. of Non-Major planning No. of planning nationally) applications determined applications determined within 13 weeks or agreed timeframe (%) Ipswich (16) 1042 1029 (98.8%) St Edmundsbury (82) 1695 1597 (94.2%) Forest Heath (99) 727 677 (93.1%) Waveney (113) 1553 1437 (92.5%) Babergh (298) 1877 1536 (81.8%) Suffolk Coastal (318) 2864 2249 (78.5%) Mid Suffolk (321) 2179 1694 (77.7%)
1.6In terms of speed of determining major planning applications (table 1), IBC ranks 19 th nationally (out of 348 LPAs across England). Importantly, every application received was determined within the statutory or agreed timeframes. 1.7 In terms of determining non-major planning applications (table 2), Ipswich ranks 16 th nationally. Only 13 applications from a total of 1042 received were determined out of time, during the two year period monitored. 1.8 Comparison against the other Suffolk LPAs (as was) is also detailed, with IBC currently determining a higher percentage of applications on time than the other LPAs.
Table 3 – Appeals: January 2017 – December 2018
Appeal type Number of Number that went Number of appeals applications to appeal allowed received Major applications 66 0 0 Minor / Householder 1042 23 (2.2% of total) 8 (0.8% of total) applications
Table 4 – Appeals determined in 2018
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PD-18-12 Development Management Annual Report 2018-19Report | 35 KB | DownloadRead as text |
PDF |
PD-18-12 Enforcement Report 2018-19 Quarter 4Report | 29 KB | Download |
PDF |
PD/18/12 Information for CouncillorsReport | 6 KB | Download |
Follow Planning & Development Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. | Decided | Open |
| 29 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 29 Jul 2026 | PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. | Noted | Open |
| 1 Jul 2026 | Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. | Decided | Open |
| 1 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.