E/21/65 Cumberland Towers Lift Replacement

Decided Executive 1 paper

Executive decided this item on Tuesday 8 March 2022. Below is the council's own wording, with the papers it was decided on.

Item126

Resolved

a) that the Maintenance and Contracts Operations Manager be authorised to proceed with the design option for the replacement of the two lift cars along with the associated structural works, electrical works, fire alarm alterations, installation of an independent stairlift serving the top floor and re-decorations to the communal areas. Reason: To raise the standard of homes to make sure they are fit for purpose for modern living and to replace building components when they reach the end of their life cycle; and to r eshape and redefine sheltered housing to make sure the Council meets changing housing needs, demands and expectations as set out in the Housing Revenue Account (HRA) Asset Management Strategy . b) that the Assistant Director of Housing, in consultation with the Section 151 Officer, Legal and Democratic Services Operations Manager and Procurement Manager, be authorised to progress with the procurement of a works contract for the reconfiguration of the lift tower, replacement of the two lift cars along with the associated structural works, electrical works, fire alarm alterations and re-decorations to the communal areas at Cumberland Towers. Reason: To enable the Council to receive and evaluate bids from appropriate contractors. c) subject to a) and b) that the Assistant Director of Housing, in consultation with the Portfolio Holders for Housing and Health and Resources, Section 151 Officer, Legal and Democratic Services Operations Manager and Procurement Manager, be authorised to enter into a contract within the proposed budget with the successful contractor for the delivery of a works contract for the reconfiguration of the lift tower, replacement of the two lift cars along with the associated structural works, electrical works, fire alarm alterations and re-decorations to the communal areas at Cumberland Towers following the procurement . Reason: To enable the Council to enter into a contract which provides value for money, with successful providers who are capable of meeting the Council’s requirements and so are the most advantageous to the Council.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

COMMITTEE: EXECUTIVE 10 REF NO: E/21/65 DATE: 8 MARCH 2022 SUBJECT: CUMBERLAND TOWERS LIFT REPLACEMENT PORTFOLIO HOLDER: COUNCILLOR NEIL MACDONALD ASST. DIRECTOR: ANDREW MEYER Short description of report content and the decision requested:

This report outlines a proposal to reconfigure the lift tower at Cumberland Towers. Executive is asked to authorise the replacement of the two lift cars along with the associated structural works, electrical works, fire alarm alterations, installation of an independent stairlift serving the top floor, and re-decorations to the communal areas; and that Officers progress with the procurement, and once complete, award a major works contract to the most economically advantageous bid within the agreed budget.

Ward(s) affected: Westgate Ward List of Appendices included in this report: N/A This report has been prepared by Paul Pledger Tele; 01473 432779 Email [email protected] This report was prepared after consultation with: Internal consultees: Assistant Director of Housing Lead Lawyer Operations Manager Maintenance & Contracts Principal Accountant Assistant Operations Manager – Procurement

The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich 2017 LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report, but which are not published and do not contain exempt information)

1. None

OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

1. IBC Housing Revenue Account Asset Management Strategy Feasibility Report by Ingleton Wood (November 2021) Executive Summary

Cumberland Towers, one of fifteen sheltered Housing Schemes, is twelve storeys high, contains 69 flats and is served by two lifts that stop at alternating floors. The lifts are estimated to be 55 years old and now require significant works and/or replacement to ensure an appropriate service can be maintained for residents in the future.

Various design options were considered and it is proposed to procure a works contract for the reconfiguration of the lift tower, replacement of the two lift cars along with the associated structural works, electrical works, fire alarm alterations, stairlift serving the top floor and re-decorations to the communal areas.

As the design stage progresses, a robust consultation exercise will be undertaken with residents and local Councillors. As well as this, a detailed communication and site management plan will be developed to keep residents informed.

A multi-disciplinary lead consultant will be employed to assist the Council with the design, procurement and contract management for the lift replacement works.

The procurement for the works contract will be based on a price:quality evaluation and be run in accordance with the Council’s procurement rules.

The estimated cost of the works over the life of the works contract, is around £800,000, which includes design fees, lift replacement works, electrical works, fire alarm upgrades and decorations.

The HRA business plan for 2022/23 onwards includes a budget in the HRA capital programme of £1m for the Cumberland Towers lift programme. This budget that has been retained in the HRA takes into account any unforeseen effects on the anticipated overall cost of the project during the detailed design stage, the time between detailed design and seeking tenders, and the potential for ongoing inflationary pressure being faced generally in the construction industry. 1. Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E/21/65 Cumberland Towers Lift ReplacementReport 660 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
DE
Councillor David EllesmereLeader, present
BR
Councillor Bryony RudkinDeputy Leader, present
SB
Councillor Sarah BarberCommittee Member, present
MC
Councillor Martin CookCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
NM
Councillor Neil MacDonaldCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, present
IF
Councillor Ian FisherCommittee Member, present

On this subject at Ipswich

Search all
  1. E/21/65 Cumberland Towers Lift ReplacementThis decision
  2. E/25/04 Residents Engagement Strategy for Cumberland TowersApproved
  3. E/17/30 Installation of a Sprinkler System in Cumberland TowersAgreed

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies