a) that the Play Area Strategy 2022 - 2027 and Play Area Action (Investment) Plan 2022 - 2027 be adopted and that the Parks and Cemeteries Operations Manager be authorised to take all necessary steps to deliver the improvement works necessary and replace the play areas identified. These steps include procurement of equipment and associated materials via the ESPO Framework and consultation with the Portfolio Holder for Environment and Climate Change, Ward Councillors and Parks Friends Groups. Reason: To improve inclusive play area provision within parks and open spaces, progressively replacing existing end-of-life and non-inclusive play areas. b) that the allocation of £3.5m funding in the MTFP 2022-2023, which includes £2.5m of capital funding, intended to meet the costs of supply and installation of identified play areas with the Play Area Action Plan, be noted. Reason: To enable the costs to be met for the supply, removal and installation of equipped play areas.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: EXECUTIVE 9 REF NO: E/21/64 DATE: 8 MARCH 2022 SUBJECT: PLAY AREA STRATEGY (2022 – 2027) PORTFOLIO HOLDER: COUNCILLOR PHILIP SMART ASSISTANT DIRECTOR: JOE TAVERNIER Short description of report content and the decision requested: This report details a proposal to adopt the Play Area Strategy 2022 – 2027 and Play Area Action (Investment) Plan 2022 - 2027.
Ward(s) affected: All List of Appendices included in this report: Appendix 1 – Play Area Strategy 2022 - 2027 Appendix 2 – Play Area Action (Investment) Plan 2022 – 2027 Appendix 3 – Play Area Strategy Action Plan – Type 1 Sites Appendix 4 – Play Area Strategy Action Plan – Type 2 Sites Appendix 5 – Map of Children’s & Young People’s Play Area Provision Appendix 6 – Definition of Objectives Used During Assessment Appendix 7 – PiPA Headlines from Site Assessment Checklist Appendix 8 – List of Play Areas Current Category 2021 - 2022 This report has been prepared by Lisa Stannard – Parks & Cemeteries Operations Manager, Email: [email protected] This report was prepared after consultation with: Internal consultees External consultees None The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich 2017 LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. None
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1.1This report seeks the adoption of a revised Play Area Strategy and associated Action Plan, both covering the period 2022 to 2027. The Play Area Strategy (Appendix 1) describes a review of current play area provision across the Borough and assessment criteria used in determining what improvements need to be made and why. The Play Area Action (Investment) Plan (Appendix 2) lists those play area sites which are in scope for improvement works, with brief notes summarising why improvements are necessary.
1.2The Council’s Medium-Term Finance Plan (MTFP) 2022-23 was approved by Council on 23 February 2022. That document includes capital funding provision for the 46 individual site improvements set out in the Play Area Action (Investment) Plan. More information about funding can be found in the MTFP report, at paragraph 3.3 (iii)(a) of Appendix 1 – MTFP 2022-23.
1.3Play area improvement works will be carried out over five financial years, starting in April 2022 (i.e. the 2022/23 FY – Year 1). Typically, the programme of works will deliver significant play area equipment upgrades and, in some cases, enhanced play area designation status. Table 1.3 provides details of the ten (10) sites scheduled for improvement works in 2022/23.
Table 1.3: Summary of Planned Play Area Improvements Sites (2022-23)
Designation Designation Estimated Ref. Site Name (Current) (Planned) Cost of Works 1 Alderman Road Rec Neighbourhood Destination £90,000 2 Castle Hill Rec Neighbourhood Destination £180,000 3 Fen Bight Circle Neighbourhood Destination £140,000 Gippeswyk Park A/B 4 Neighbourhood Neighbourhood £150,000 Toddler+Teen 5 Girton Way Pocket Removed £5,000 6 Hawke Road Neighbourhood Neighbourhood £120,000 7 Holywells Park Destination Destination £250,000 8 Talmash Gardens Pocket Removed £5,000 9 Village Green A Community Community £30,000 10 Village Green B Pocket Pocket £30,000 Total: £1,000,000 (including Capital funding of): £500,000 (including section 106 funding of): £500,000
1.4MTFP 2022-23 makes provision for £3.5m of funding for play area improvements, including additional funding from S106 planning agreements. The new capital budget element of that provision is designed to kick start this five-year programme of improvements to our Play Areas – at £0.5m per annum, from April 2022. 2. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.