that Executive authorises the Director - Operations & Place, in consultation with the Assistant Director - Finance, Head of Legal Services, Head of Procurement, Portfolio Holder for Resources and Portfolio Holder for Planning and Museums, to enter into a contract with a Gallery Fit-Out and Interpretation contractor, provided this can be achieved within the cost estimate provided in exempt Appendix 1 of the report. Reason: To enable the contract to be executed and the works to proceed.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
2.1On 6th February 2024 (E/23/48), Executive authorised officers, in consultation with the Portfolio Holder for Resources and Portfolio Holder for Planning and Museums, to enter into a contract with a Gallery Fit-Out and Interpretation contractor for the Ipswich Museum Redevelopment, provided this could be achieved within the cost estimate provided in that report.
2.2This cost estimate was calculated during the design stage of this element of the project using the best information available at that time.
2.3Since February 2024, the designs for the gallery fit out and interpretation have been further developed and are now at RIBA Stage 4, which is the final stage of the technical design.
2.4The cost estimate has now been recalculated, based on the final technical design and now includes the digital elements of the interpretation plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.