E/25/58 Retaining Wall at Cambridge Drive

Decided Executive 3 papers

AI summaryIpswich Borough Council Executive has authorised procurement of a specialist contract to repair and rebuild the 154-metre retaining wall along Cambridge Drive in Stoke Park Ward, with works set to start in summer 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement and contract award authorised
MoneyWithin existing capital budgetHRA 30-year Business Plan, 2026/27, Exempt Appendix 3
What happens nextTender and award in 2026Open tender, start works summer 2026
Who it affectsCambridge Drive residents, road usersStoke Park Ward, Ipswich

What was decided

The Executive authorised the Assistant Director for Housing, in consultation with the Section 151 Officer, Head of Legal Services and Head of Procurement, to progress the procurement contract for works to the retaining wall. Report 14.1

The Executive authorised the Assistant Director for Housing, in consultation with the Housing and Resources Portfolio Holders, Head of Finance, Head of Legal Services and Head of Procurement, to award the contract, provided it is within the capital budget in Exempt Appendix 3. Report 14.2

Why

The retaining wall is in poor condition and could pose a risk to residents, pedestrians, and road users if no intervention is made. Report 2.6

The Council wants to ensure its assets are effectively maintained and improve neighbourhood quality. Report 2.5, 3.2, P26

An open tender was preferred over a national framework agreement so that local small and medium enterprises can bid and support the local economy. Report 4.2, P34

What happens next

Procurement will run as a single stage open tender under the Procurement Act 2023 and Procurement Regulations 2024, with notices on Suffolk Sourcing and the UK Procurement Platform. Report 2.13, 2.14, 11.1

Tenders will be assessed on a 60% price and 40% quality split, subject to bidders meeting mandatory financial and technical standards. Report 2.16

Works are expected to start in the summer of 2026, with the contract running for 6 months and a possible 3 month extension for unforeseen site conditions; an Environmental Impact Assessment and Planning and Highways advice will be completed first. Report P15, P21, 2.11, 7.1

The money

  • Within existing capital budget (Exempt Appendix 3) Funding for the 9 month Cambridge Drive retaining wall contract Report 10.1, 10.2, 10.3

Options considered

  • Chosen: Option 1: Tender a 6 month contract with an optional 3 month extension via open tender. Reaches local SMEs, ensures a specialist contractor and value for money Report 4.1, P31, P32
  • Rejected: Option 2: Use a national framework agreement. Frameworks exclude local SMEs and reduce the Council's control over terms and conditions Report 4.2, P34, P35
  • Rejected: Reserve the contract award to the Executive itself for a future meeting. Not pursued; Executive instead delegated award to the Assistant Director for Housing Report 14.3, P73

Implications

  • Risk: Risks include reputational damage and Health and Safety failure to pedestrians, residents and road users from a failing wall; mitigated by policy, monitoring, contractor vetting and Health and Safety controls. Report P40, 2.6
  • Risk: Supply chain failure risk mitigated by vetting subcontractors, contractor financial and technical checks, and governance arrangements. Report P41
  • Equalities: An Equalities Impact Assessment concluded there is no significant impact on protected groups under the contract; bidders must have robust equal opportunities policies. Report 8.4, 8.5
  • Climate: An Environmental Impact Assessment will be completed before works proceed, and environmental objectives will be written into the contract to reduce carbon emissions. Report 7.1, 7.2, P27
  • Legal: Procurement will comply with the Procurement Act 2023, the Procurement Regulations 2024, the Council's Contract Standing Orders, CDM Regulations and the New Roads and Street Works Act 1991. Report 11.1, 11.2, 12.2, 2.10

Who and where

  • Residents, pedestrians and road users along Cambridge Drive in Stoke Park Ward Report 2.6
  • Local small and medium enterprises invited to bid for the works Report P21, P34
  • Tenants of the surrounding Cambridge Drive housing developed in the 1970s Report 2.1, 5.2

Timeline

  • Summer 2026: Anticipated start of the contract for retaining wall works Report P15
  • 2026/27 financial year: Capital budget provision for the project within the HRA 30 year Business Plan Report 10.1, 10.2
  • 6 months plus optional 3 months: Length of the proposed one-off contract, with extension subject to site conditions Report P21

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account that funds council housing services and assets.
  • MTFP: Medium Term Financial Plan, the Council's multi-year budget planning document.
  • NRSWA: New Roads and Street Works Act 1991, which governs road and street works by utilities and contractors.
  • CDM Regulations: Construction, Design and Management Regulations, covering health and safety duties for construction projects.
  • EIA: Environmental Impact Assessment, used to identify and mitigate environmental effects of a project.
  • SME: Small and Medium Enterprise, a business below specified size thresholds.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item125

Resolved

a) That Executive authorises the Assistant Director for Housing, in consultation with the Section 151 Officer, Head of Legal Services and Head of Procurement, to progress with the procurement contract for works to the retaining wall as detailed in paragraph 4.1 of the report. Reason: To enable bids to be received and evaluated from appropriate contractors. a) Subject to a), that Executive authorises the Assistant Director for Housing, in consultation with the Housing Portfolio Holder, Resources Portfolio Holder, Head of Finance, Head of Legal Services and Head of Procurement, to award the contract to complete the works to the retaining wall, provided it is within the capital budget in Exempt Appendix 3 to the report. Reason: To enable the Council to enter a contract which provides value for money, with a successful provider who can meet the Council’s requirements which is the most advantageous to the Council.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

Background

2.1The Cambridge Drive development encompasses Magdalene Close through to Downing Close and was developed in the 1970s. The area has a mix of low-rise flats, semi-detached and terraced house style properties.

2.2Along Cambridge Drive, following down from the hill beyond the shopping parade, there is a large structural wall. This wall spans approximately 154 metres and is between 1.1 to 1.3 metres in height. The highest point of this wall is at the Magdalene Close junction and reduces in height towards the Downing Close junction.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E-25-58 Appendix 1: Engineers ReportAppendix 5.6 MB Download
PDF
E-25-58 Appendix 2: EQIAAppendix 69 KB Download
PDF
E/25/58 Retaining Wall at Cambridge DriveReport 360 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
NM
Councillor Neil MacDonaldLeader, present
BR
Councillor Bryony RudkinDeputy Leader, present
JC
Councillor John CookCommittee Member, present
MC
Councillor Martin CookCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
JR
Councillor Jane RileyCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, present
LT
Councillor Lucy TrenchardCommittee Member, present
IF
Councillor Ian FisherCommittee Member, present

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies